US3602302A - Oil production system - Google Patents
Oil production system Download PDFInfo
- Publication number
- US3602302A US3602302A US875350A US3602302DA US3602302A US 3602302 A US3602302 A US 3602302A US 875350 A US875350 A US 875350A US 3602302D A US3602302D A US 3602302DA US 3602302 A US3602302 A US 3602302A
- Authority
- US
- United States
- Prior art keywords
- swivel
- header
- lines
- vessel
- well
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 60
- 239000012530 fluid Substances 0.000 claims abstract description 88
- 238000012360 testing method Methods 0.000 claims abstract description 62
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 24
- 230000004087 circulation Effects 0.000 claims description 46
- 239000003921 oil Substances 0.000 claims description 21
- 238000005086 pumping Methods 0.000 claims description 17
- 238000003860 storage Methods 0.000 claims description 10
- 239000003129 oil well Substances 0.000 claims description 7
- 239000010779 crude oil Substances 0.000 claims description 5
- 239000011159 matrix material Substances 0.000 claims description 2
- 238000000034 method Methods 0.000 abstract description 7
- 238000007667 floating Methods 0.000 abstract description 6
- 238000012545 processing Methods 0.000 abstract description 2
- 238000012423 maintenance Methods 0.000 description 6
- 230000009471 action Effects 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 125000006850 spacer group Chemical group 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000000712 assembly Effects 0.000 description 2
- 238000000429 assembly Methods 0.000 description 2
- 238000004891 communication Methods 0.000 description 2
- 230000013011 mating Effects 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 241000191291 Abies alba Species 0.000 description 1
- 230000004308 accommodation Effects 0.000 description 1
- 230000004913 activation Effects 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 239000007789 gas Substances 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000033001 locomotion Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000012188 paraffin wax Substances 0.000 description 1
- 230000000135 prohibitive effect Effects 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPINGÂ
- B63B21/00—Tying-up; Shifting, towing, or pushing equipment; Anchoring
- B63B21/50—Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
- B63B21/507—Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers with mooring turrets
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B23/00—Apparatus for displacing, setting, locking, releasing, or removing tools, packers or the like in the boreholes or wells
- E21B23/08—Introducing or running tools by fluid pressure, e.g. through-the-flow-line tool systems
- E21B23/12—Tool diverters
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/02—Surface sealing or packing
- E21B33/03—Well heads; Setting-up thereof
- E21B33/068—Well heads; Setting-up thereof having provision for introducing objects or fluids into, or removing objects from, wells
- E21B33/076—Well heads; Setting-up thereof having provision for introducing objects or fluids into, or removing objects from, wells specially adapted for underwater installations
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/01—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells specially adapted for obtaining from underwater installations
- E21B43/017—Production satellite stations, i.e. underwater installations comprising a plurality of satellite well heads connected to a central station
- E21B43/0175—Hydraulic schemes for production manifolds
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPINGÂ
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/44—Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
- B63B2035/448—Floating hydrocarbon production vessels, e.g. Floating Production Storage and Offloading vessels [FPSO]
Definitions
- the barge carries oil production equipment for processing well fluid.
- a plurality of flexible flow lines extend down through the swivel to connect with a plurality of individual wellheads, or with one or more central manifolds on the water bottom.
- PRODUCTION SYSTEM BACKGROUND OF THE INVENTION 1. Field of the Invention Offshore floating oil production systems.
- a protected swivel is the subject of U.S. Pat. No. 3,279,404, however the swivel is midship and the vessel willnot of itself maintain its head into wind and sea.
- An elongated vessel having a swivel near the bow thereof carries oil production equipment and storage tanks for storing large quantities of processed oil.
- a plurality of flexible fluid lines extend through the swivel and connect with underwater oil wells and at the vessel flow control means are provided for selectively connecting the lines with a testing separator and metering station for testing wells, and a pumping station for delivering and retaining tool strings inserted into selected lines.
- FIG. 1 is a slide elevational view, with portions broken away, of an offshore floating oil production system in accordance with one embodiment of the present invention
- FIG. 2 is a cross-sectional view of the swivel shown in FIG. 1;
- FIG. 3 is a top view of the swivel illustrated in FIG. 2;
- FIG. 4 is a perspective view of a portion of the swivel illustrated in FIG. 2;
- FIG. 5 is a plan view of the apparatus illustrated in FIG. 1;
- FIG. 6 is a diagrammatic flow diagram of the apparatus shown in FIG. 1;
- FIG. 7 illustrates the arrangement of apparatus for performing certain operations
- FIGS. 7A and 7B are flow diagrams of the apparatus of FIG. -7 in two different modes of operation;
- FIG. 8 illustrates another embodiment of the present inventron
- FIG. 9 illustrates the switching network of FIG. 8 in somewhat more detail.
- FIG. 9A is a table of various valve openings for FIG. 9.
- FIG. 1 there is illustrated an elongated vessel 10 on station above the water bottom 12.
- the vessel 10 may be in the form of an elongated barge and includes a full compliment of production equipment 14 such as high and low-pressure separators, free-water knockouts, treaters etc. situated on the open deck, and additionally includes a plurality of storage tanks 16 connected to receive the output from the production equipment 14'for storing treated crude oil.
- production equipment 14 such as high and low-pressure separators, free-water knockouts, treaters etc.
- a well 20 Positioned near thebow 18 and within the boundaries of the vessel is a well 20 extending from the deck 21 to the bottom 22 of vessel 10. Positioned within the well 20 is a swivel means in the form of mooring swivel 24 extending from the deck to below the water surface and held in position by mooring means in the form of a plurality of anchor chains 26 (only two are shown) firmly secured to the water bottom 12 so that the vesselwill weathervane about the swivel 24 to maintain the bow portion headed into the waves and wind.
- thrust units 28 are provided at the stern of the vessel 10 and are operable to maintain the vessel on the most favorable heading.
- crews living quarters 29 be established forward of the swivel 24 since the vessel always weathervanes into'the wind and the bow may serve as the place of last refuge for the crew in the event of fire.
- Flexible hose assemblies 32 aid 33 from underwater wells 36 and 37 extend up through the swivel 24 to certain apparatus on the swivel.
- a crane 40 is provided forward of the swivel 24 to aid in the handling of various pieces of equipment such as lubricator 42, as will be explained.
- FIG. 2 A more detailed, cross-sectional view of the swivel and part of the vessel, is illustrated in FIG. 2.
- the swivel 24 has a large diameter tube 25 situated within the well 20 and an upper flange portion forming a swivel platform 47.
- the swivel 24 is rotatably supported by a plurality of roller units 50 extending from the bottom of swivel platform 47 to a circular track 51 on the deck 21.
- the swivel 24 is additionally restrained laterally by a set of upper roller units 53 extending between the tube 25 and track 54, and a plurality of lower roller'units 57 extending between the tube 25 and track 58.
- Each anchor chain 26 extends up through a flange 60 at the bottom of the swivel 24, through the swivel platform 47 and secured thereto at respective securing points 62.
- the hose assembly 32 includes at least a pair of fluid carrying lines in the form of production line 65 and circulation line 66.
- a third line 67 is a control line andmay include power conveying means for actuating valves at the underwater well such means being, for example, hydraulic pneumatic or electrical. Alternatively the control line 67 may be eliminated and the valves controlled automatically in response to coded acoustic signals transmitted through the water medium.
- the lines 65, 66 and 67 are held together as a unit by means of a spacer 69 such spacers-being distributed along the length of the assembly.
- Bouyant materials 70 also disposed along the length of the assembly prevent the assembly from possibly dragging on the water bottom.
- the three lines 65, 66 and 67 pass up through a relatively small diameter vertical tube 73 within the swivel 24, and are disconnectable by means of a hose assembly connector 75.
- Production line 65 and circulation line 66 pass up through a support 77 positioned on the swivel platform 47.
- Hose assembly 33 connected to well 37 is identical to hose assembly 32 in that it contains a plurality of flexible fluid conveying lines such as production line 84, circulation line 85 and a control line 86, passing up through vertical tube 88 and being disconnectable by means of hose assembly connector 90.
- the hose assembly 33 includes the spacer 92 and buoyant material 93 to prevent it from dragging on the water bottom and the assembly passes up through support 95 at the top of the swivel platform 47.
- well fluid for example from well 36 passes up the production line 65 through a first or master valve 100, into connecting pipe 102, through a second or wing valve 104 and into a centrally located vertical header 107, a header being a tube, chamber or similar structure to which a bank or series of tubes or other connections are joined to permit fluid flow.
- Suitable flow control units such as chokes may be included but are not shown herein.
- Well fluid from well 37 passes up the production line 84 to the master valve 110, through connecting pipe 112 and wing valve 114 into the header 107,
- well fluid from all of the other wells in the field flow into header 107 and the comingled well fluid iscarried to the production equipment by production hose 116 connected to the header 107 by means of a rotary pipe joint 1 19,
- a test and metering station which includes a metering separator where the components of the well fluid are separated and individually metered. Accordingly means are provided for selectively controlling fluid flow in individual ones of the fluid lines to place individual wells on test.
- This means in the embodiment of FIG. 2, includes an annual header 122 concentrically disposed about header 107, and a plurality of valves for connecting the production line from each well to the annular header. Since the annular header 122 is utilized in test operations it will herein be termed the test header.
- valve 124 With respect to well 36 there is provided valve 124 which when open will divert the flow from connecting pipe 102 into connecting pipe 126 and test header 122. During such operation wing valve 104 would normally be closed.
- fluid from production line 84 may be diverted from connecting pipe 112 by opening valve 129 so that produced fluid may enter the test header 122 by way of connecting pipe 130.
- Wing valve 114 would normally be closed while the remaining wing valves from the other assemblies would be open such that during testing operations well fluid from only one well is diverted into the test header 122.
- the test header 122 communicates with a testing station in a manner to be hereinafter described.
- the circulation line 66 includes a first or master valve 134, and a second or wing valve 136. When both of these valves are open, and a third or swabbing valve 138 is closed, fluid communication is established between circulation line 66 and a second annular header l40'herein termed the circula tion header and concentrically disposed about the header 107.
- fluid flow in circulation line is controlled by a first valve 142 and a second valve 144 both of which are operable when open to communicate fluid with the circulation header 140.
- valves at the underwater well may be controlled in a number of different ways including acoustic means, for clarity no particular connections are illustrated for the control lines 67 and 86.
- Insertion of a pump down tool string into a fluid line such as production line 65 may be accomplished with the provision of a lubricator 42.
- the tool string is inserted into the lubricator 42 which is connected to the production line such as by flange connection 146. Pressure is then applied at the top of the lubricator while swabbing valve 148 and master valve are open to send the tool string out of the lubricator and past the level of wing valve 104. If the tool string to be inserted is very long, the valving means at the underwater wellhead can be closed and the entire length of flow line used as a lubricator.
- swabbing valves 138, 148, 150 and 151 tool strings may be inserted into respective fluid lines 66, 65, 84 and 85.
- Means including guide or track extending around the periphery of the swivel platform 47, are provided for connecting the test header 122 and circulation header 140 to certain equipment on the vessel. Such connections are better illustrated in FIG. 3 which is a plan view of the swivel platform 47 of FIG. 2 with the valves and certain other equipment omitted for clarity.
- a first connecting means such as a rotary pipe joint 159 and a second connecting means such as rotary pipe joint 161.
- Test header 122 is connected to the rotary pipe joint 159 by means of fluid conveying conduit 163 and circulation header 140 is connected to rotary pipe joint 161 by means of fluid convening conduit 164.
- First and second reels and 171 on the vessel deck have flexible hoses 173 and 174 coiled thereon and connected respectively to rotary pipe joints 159 and 161.
- the other end of hose 173 is connected through a rotary pipe joint to fluid conduit 176 and the other end of flexible hose 174 is connected through a rotary pipe joint to fluid conduit 177.
- hoses 173 and 174 will be pulled from their respective reels I70 and 171 and will be placed in the track means 155. Another view of this operation is illustrated in FIG. 5.
- reels 170 and 171 When the swivel platform 47 relatively moves in a clockwise direction reels 170 and 171 will take up the slack of the hoses 173 and 174.
- This arrangement provides fluid communication, and prevents entanglement as the vessel rotates about the swivel.
- the relative rotation may be for a full turn or more depending upon the length of hose 173 or 174.
- FIG. 6 there is illustrated a flow diagram for the underwater well 36, Those components previously described in other figures have been given the same reference numeral. At the upper portion of the figure are the components illustrated in FIG. 2 for selective control of the underwater well 36. At the lower portion of the figure there is illustrated a pile structure 188 secured to the water bottom 12 and which supports a hose assembly connector 190.
- the production line 65 extending from the connector 190 over to the well 36 may be in the fonn of steel tubing having curvatures 192 of sufficient radius, for example 5 feet, to enable passage of long tool trains and would lie on the bottom 12.
- the circulation line 66 on the bottom may similarly be of steel tubing with curvatures 193 to enable tool train passage.
- the underwater well 36 includes a Christmas tree 193 with the production line 65 being connected with the production string 195 by means of wing valve 197 and master valve 198.
- Circulation line 66 is connected to the circulation string 200 by means of wing valve 202 and master valve 203.
- the apparatus of the present invention allows such maintenance operation to be performed by the use of conventional pump down tool techniques and to this end reference is now made to FIG. 7.
- FIG. 7 illustrates a flow diagram and components already described have been given the same reference numeral.
- Onboard apparatus for testing and servicing the various wells includes a test separator and metering station 210 and a pump and metering station 212 in conjunction with a plurality of valves 214 through 217.
- valves 124 and 214 are open.
- Well fluid then proceeds from production string 195 to production line 65, through valve 124 into the test header 122, out of the test header and into fluid line 176 by way of the rotary pipe joint 159 and flexible hose 173 wound on reel 170.
- fluid conduit 176 From fluid conduit 176 the fluid passes through valve 214 and into the test separator and metering station 210.
- the well fluid as it emerges from the well is at very high pressures, for example thousands of p.s.i. and the test separator at station 210 reduces the pressure to atmospheric.
- valve 124 may be closed and a similar wing valve associated with another well may be opened to deliver that wells fluid to station 210.
- valves 136 and 217 may be opened to establish fluid flow from the circulation line 66 into circulation header 140 through rotary pipe joint 161 and flexible hose 174 to the reel 171 and fluid conduit 177 and into the test station 210 through valve 217.
- FIG. 7 For maintenance operation where it is required to send a tool string down into the production string 195, the arrangement of FIG. 7 may be utilized as shown in FIG. 7A, which for clarity, shows only those conduits and valves involved in the operation.
- Lubricator 42 containing a tool string is connected as previously described and valves 148 and 124 are opened. By suitable means connected to the lubricator the tool string is sent past valve 148 which is thereafter closed.
- Pumping station 212 pumps quiescent crude from tank 16, through valve 215 and into production line 65 behind the tool string, by the path including fluid conduit 176, flexible hose 173, rotary pipe joint 159, header 122 and valve 124.
- a return for the fluid displaced ahead of the tool string is provided by the path including circulation line 66, valve 136, circulation header 140, rotary pipe joint 161, flexible hose 174, fluid conduit 177, valve 217, and into the test station 210 where it is returned to the tank 16.
- Pumping station 212 pumps the quiescent crude down the circulation line 66 by the path including valve 216, fluid conduit 177, flexible hose 174, rotary pipe joint l6l', circulation header and valve 136. Fluid displaced ahead of the tool string in production line 65 is returned to the testing station 210 by the path including valve 124, test header 122, rotary pipe joint 159, flexible hose 173, fluid conduit 176 and valve 214.
- the pumping station 212 includes metering means for determining the approximate position of the tool in the line 65, since there is a direct relationship between its position and the quantity of quiescent crude pumped.
- the circulating line 66 could also be used to provide gas to the wells for artificial lift for which purpose there is illustrated a gas lift system 220.
- Unloading of the vessel 10 can be accomplished by having a tanker come alongside, special fendering and mooring winches being provided aboard the vessel 10 to prevent metalto-metal contact between the hulls and to maintain good control over the tanker.
- the tanker could approach from astern and tie to a single mooring line from the stern of the vessel 10 the oil being transferred from storage tanks 16 through a floating hose; if the tanker were to go astern slowly on its engine the two hulls need never come in contact.
- some shipmasters might prefer the former method which provides for the tanker to be well secured alongside the vessel 10.
- a typical vessel 10 may have a length in the order of 600 feet with a beam or width of 80 feet and a depth from top deck to the bottom of the vessel of 50 feet.
- the storage capacity of such vessel may be 300,000 barrels and approximately 16 wells may be serviced by means of the arrangement described. Larger vessels and swivels may accommodate a larger number of wells however there is a point at which practical limitations on the size of the swivel will limit the number of wells which can be accommodated within it. For a greater number of wells, the arrangement of FIG. 8 may be utilized.
- FIG. 8 there is illustrated the swivel 24 within the vessel 10 at the surface and depending from the swivel 24 and extending toward the water bottom 12 is a plurality of flexible fluid conveying conduits 224, 225 and 226 with the flexible conduit 224 being a production line, flexible conduit 225 being a test and tool line, and flexible conduit 226 being the circulation line.
- These flexible conduits are held in spaced relationship by means of spacers 228 with buoyant material 229 as previously described.
- a gathering station 236 Positioned on the water bottom 12 is a gathering station 236 which includes a landing base 238 concreted in position within a pile 240 in the water bottom.
- a manifold means 242 which includes a carrier unit 244 having a guide pipe 245 for guiding the unit into its position on the landing base 238.
- the manifold means 242 is connected to the landing base 238 by a plurality of detachable connectors 248.
- the manifold means 242 includes header 252 in addition to a plurality of test and tool lines 225a to 225n having respective valves 254a to 254n. Each line 225a to 225;: is connected with the header 252 by means of respective branch lines 2580 to 258n having respective valves 459a to 259n.
- the test and tool lines 225a to 225n are selectively connectable to test and tool line 225 through a switching network 261.
- the manifold means also includes a plurality of circulation lines 226a to 226a having respective valves 260a to 260n which connect the lines 2260 to 226n with the circulation line 226.
- connections are provided between lines 225a to 2251 and respective lines 225a to 225n' which carry the well fluid from respective wells of which two, 264 and 265, are illustrated. Connection is also made between lines 226a to 226:: and lines 226a to 226n' which constitute the circulation lines for the individual wells.
- the fluid lines extending from the base 238 are suitably valved to allow for detachment of the manifold means 242.
- the comingled production lines 224, the test and tool line 225 and the circulation line 226 extend from the manifold means 242 up through the swivel 24 in the vessel 10 and at the swivel platform 47 rotary pipe joint 268 connected to the comingled production line 224 connects the well production with the vessel-carried production equipment by way of the hose 270.
- Means are provided for connecting the test and tool line 225 and circulation line 226 with the pumping and the test stations as previously described.
- the means may include respective pipe connections to the periphery of the swivel platform 47 and thereafter to a hose and reel arrangement as previously described.
- suitable valving means may be supplied to these lines at the swivel platform 47 and thereafter the lines may be directly connected with a pumping and test station for those situations where relatively little swivel action takes place or for those instances where some degree of twisting of lines may be tolerated.
- Valves 254a to 254n in the test and tool lines and valves 260a to 26011 in the circulation line are closed; all other valves are open.
- Well fluid from the various wells flow up the respective lines 225a to 225n' and into the header 252 through respective valved branch lines 258a to 258n.
- the comingled fluids then travel up the flexible line 224, through the swivel and to the production equipment.
- valve 259a in the branch line 258a is closed and valve 254a in line 225a is opened so that the well fluid from well 264 travels up the test and tool line 225, through the swivel 24 and to a test station as described previously with respect to FIG. 7. Subsequent to the test, valve 259a is again opened and valve 254a is closed.
- a maintenance operation is to be performed at one of the wells, for example well 265, and such operation requires the use of a tool string
- such tool string may be inserted in the test line 225 at the swivel platform 47.
- Valve 259k in branch line 258b is closed and valve 254b in line 225b as well as valve 26Gb in circulation line 226b is opened.
- the tool string is pumped down the test and tool line 225, enters the switching network 261 where it is directed-to line 225b and thereafter to the well 265.
- the tool string may be returned'by the method illustrated in FIG. 7B, the'tool string passing up through the switching network 261 and after its recovery at the swivel platform 47 the valves may be returned to their respectively normally operating conditions.
- the switching network 261 is operative upon proper command from the surface, such as by hydraulic, pneumatic, electric or acoustically encoded signal activation to switch a tool string in test line 225 from the vessel 10 to any selected one of a number of underwater sells connected to the gathering station 236.
- a typical switching network may include various branch lines with fluidic switching such as illustrated in FIG. 9 wherein a switching network for controlling nine wells is shown.
- the switching network of FIG. 9 includes a plurality of fluidic switches 280 to 283 each having an input line, three output lines and two control lines. The lines for each fluidic switch are labeled accordingly and operation is such that if a high-pressure fluid is supplied to the first control line, the tool will be forced over to the third output line.
- control unit 286 which includes a source of high-pressure fluid and which has eight outputs controlled by eight valves designated V1 to V8.
- a tool string at the input of fluidic switch 280 may be directed to any one of the nine wells by selective opening of one or more of the valves V1 to V8. If the tool string is to be sent to well 1, valves V3 and V8 are opened whereby the tool string at fluidic switch 280 is forced by the high-pressure fluid in the second control line over to the first output line as is the case in fluidic switch 281. For servicing well 5, all of the valves are closed (or all of the valves may be opened) such that the tool exits from fluidic'switch 280 at the second output with a similar exit from fluidic switch 282.
- the table of FIG. 9A designates the particular valve or valves which are to be opened in order to service the designated wells.
- Fluidic switching may also be accomplished with a fluidic switch having one input and two outputs and two control lines however many more fluidic switches would be required.
- a plurality of gathering stations may be provided in conjunction with a header arrangement on the swivel 24.
- the arrangement would include a first header for valved connection with all the comingled production lines, a second header for valved connection with all the circulation lines, and a third header for valved connection with all the test and tool lines. Fluid connection with the pumping test and metering stations would be similar to that previously illustrated.
- Offshore oil production apparatus comprising a. an elongated vessel having a well extending vertically therethrough to below the vessels waterline;
- swivel means positioned within said well, and including a swivel platform at the upper portion thereof;
- the swivel means includes a relatively large diameter vertical tube depending from the swivel platform;
- each production line and each circulation line of each underwater well extends up through the swivel means; and which includes B. a test header and a circulation header positioned on the swivel platform;
- Apparatus according to claim 3 which includes:
- valve connections at said gathering station for combining the production lines of a plurality of underwater wells
- D. means connecting the combined production lines with a first one of the flexible fluid carrying lines extending up the swivel means and for connecting the combined circulation lines with a second one of the flexible fluid carrying lines extending up the swivel means.
- the swivel means is located near the bow of the vessel
- the first header means is centrally located on the swivel platform, and which includes B. a rotary pipe joint connecting the first conduit means to the first header means.
- the production header and circulation header are concentrically disposed about the first header.
- the pumping station pumps crude oil from one of the storage tanks.
- the pumping station includes metering means for metering the quantity of the crude oil pumped, for determining the approximate location of a tool string in a selected one of the flexible fluid carrying lines.
- Apparatus according to claim 1 which includes:
- connection means respectively connected to said second and third header means
- E a pair of hose reels each operable to wind and unwind carried hose;
- F one end of the hoses from said pair of hose reels being connectable with respective ones of said pair of connection means;
- G means for selectively connecting the other end of said hoses to the test separator and metering station and the pumping station.
- connection means are disposed on the periphery of the swivel platform; and which includes B. a guide on said periphery of the swivel platform for receiving respective hoses from the hose reel when the vessel and swivel means relatively rotate.
Abstract
An elongated floating vessel in the form of a large fluid capacity barge has a swivel near the forward end thereof which passes down through the vessel and is securely moored to the water bottom so that the barge may weathervane about the swivel. The barge carries oil production equipment for processing well fluid. A plurality of flexible flow lines extend down through the swivel to connect with a plurality of individual wellheads, or with one or more central manifolds on the water bottom. Servicing of the individual wells is made possible by apparatus on the swivel which allows for selective well testing and selective well access for a full range of pump down tool techniques.
Description
United States Patent [72] Inventor Charles S. Khith Baltimore, Md. [21] Appl. No. 875,350 [22] Filed Nov. 10, 1969 [45] Patented Aug. 31,1971 [73] Assignee Westinghouse Electric Corporation Pittsburgh, Pa.
54 on. PRODUCTION SYSTEM 13 Claims, 12 Drawing Figs.
[52] U.S. Cl 166/.5, 1 14/5 [51] lnt.Cl E21b43/01 [50] Field oiSearch 175/5,7,8;
[56] References Cited UNITED STATES PATENTS 2,699,321 1/1955 Nelson 175/8 3,111,692 11/1963 Cox 175/8 X 3,279,404 10/1966 Richardson 1 14/5 3,335,690 8/1967 Busking 114/230 Primary ExaminerStephen J. Novosad' Assistant Examiner-Richard E. Favreau Attorneys-F. H. Henson, E. P. Klipfel and D. Schron ABSTRACT: An elongated floating vessel in the form of a large fluid capacity barge has a swivel near the forward end thereof which passes down through the vessel and is securely moored to the water bottom so that the barge may weathervane about the swivel.
The barge carries oil production equipment for processing well fluid. A plurality of flexible flow lines extend down through the swivel to connect with a plurality of individual wellheads, or with one or more central manifolds on the water bottom.
Servicing of the individual wells is made possible by apparatus on the swivel which allows for selective well testing and selective well access for a full range of pump down too] techniques.
PATENTEU AUG31 I97;
SHEET 3 0F 7 ATENTEU AUGSI l97l SHEET 5 BF 7 mm 6E QZEUFME OZEEDm PATENTED M831 IBYi 3.602.302
SHEET 7 0F 7 INPUT 28g- F|G.9 ls t. CONTROL 2nd. CONTROL ls'r. OUTPUT 3rd OUTPUT 'NPUT 2M1 OUTPUT g is! CONTROL INPUT 2nd CONZTBRZOL /|NPUT 283}- v2 v3! W4 VET! v' YT} L -1 L- .1 L- J 2nd 2nd is? 2nd 3rd 3 d 3rd l 2 3 4 s s 7 a 9 WELLS WELLS WELLS v1 v2 v3 v4 vs vs v7 ve CONTROL H 9A WELL OPEN VALVE v3,va
3 v2,va
5 NONE 9 VI,V6
011. PRODUCTION SYSTEM BACKGROUND OF THE INVENTION 1. Field of the Invention Offshore floating oil production systems.
2. Description of the Prior Art A major problem in producing oil from underwater fields which lie in deep water is the cost of the bottom supported surface-piercing fixed platforms employed to support the control and treating equipment. Additionally the possibility of earthquakes is a major factor in increased platform costs.
Another major problem in producing oil from underwater fields is that they are sometimes located so far from land that the cost of moving the oil ashore is very high or even prohibitive. The capital and operating costs of any given size of pipeline are direct functions of its length and it is obvious that the length can exceed economic feasibility.
One proposal for eliminating the pipelines contemplates utilization of a floating semisubmersible platform such as in U.S. Pat. No. 3,111,692, having well production and storage facilities and which will be able to stay on station without severely being affected by wave action, due to its unique configuration. An undesirable factor however is that such semisubmersibles are very sensitive to the amount and location of load and are inherently inefficient in their ability to support and enclose a large amount of oil.
It is therefore a primary object of the present invention to provide an economical means of producing oil in remote deep water locations or in near shore areas where it is not desirable to bring the production directly ashore by pipeline.
Storage barges for offshore oil wells have been described which utilize a ship form facility in conjunction with a swivel so that the facility may weathervane to reduce the effect of wave action. U.S. Pat. Nos. 3,335,690 and 3,407,768 describe such structures. In 3,335,690 the swivel is located forwardly of the vessel and presents a dangerous condition for personnel who may have to work on the swivel, particularly in adverse weather conditions. In addition, the very limited workspace provided makes necessary operations to be carried out on the various wells extremely difficult. In 3,407,768 the swivel extends down to a point above the water surface and the structure presents an overhang which in heavy weather is a serious hazard to the ship. The shock and vibration experienced by the vessel in such weather would subject it to severe stresses which might result in catastrophic failure.
The patents illustrate a single hose extending below the surface of the water but the necessary equipment for achieving the aforestated object of the present invention is not disclosed.
A protected swivel is the subject of U.S. Pat. No. 3,279,404, however the swivel is midship and the vessel willnot of itself maintain its head into wind and sea.
U.S. Pat. No. 2,699,321 and page 99 of the July 1968 issue of World Oil each show a craft which has a large diameter spindle extending through the craft with a rigid connection to the bottom such rigid connection being a plurality of tubular metal pilings in the patent, and a 3 or 4 foot diameter steel tube in the article. Such rigid connection, although providing for weathervaning action of the vessel (yaw) and rise and fall of its (heave), permits little or no freedom in pitch, roll, surge, or sway. Since the great mass and waterplane area of the vessel make it virtually impossible completely to restrain these motions, such rigid connection must necessarily be in grave jeopardy when large seas are acting upon the vessel.
None of the related prior art existing or proposed-systems disclose the necessary means for practicing another feature of the present invention. which is the provision interrelationship of various equipment for performing maintenance and test operations on the wells.
SUMMARY OF THE INVENTION An elongated vessel having a swivel near the bow thereof carries oil production equipment and storage tanks for storing large quantities of processed oil. A plurality of flexible fluid lines extend through the swivel and connect with underwater oil wells and at the vessel flow control means are provided for selectively connecting the lines with a testing separator and metering station for testing wells, and a pumping station for delivering and retaining tool strings inserted into selected lines.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a slide elevational view, with portions broken away, of an offshore floating oil production system in accordance with one embodiment of the present invention;
FIG. 2 is a cross-sectional view of the swivel shown in FIG. 1;
FIG. 3 is a top view of the swivel illustrated in FIG. 2;
FIG. 4 is a perspective view of a portion of the swivel illustrated in FIG. 2;
FIG. 5 is a plan view of the apparatus illustrated in FIG. 1;
FIG. 6 is a diagrammatic flow diagram of the apparatus shown in FIG. 1;
FIG. 7 illustrates the arrangement of apparatus for performing certain operations;
FIGS. 7A and 7B are flow diagrams of the apparatus of FIG. -7 in two different modes of operation;
FIG. 8 illustrates another embodiment of the present inventron;
FIG. 9 illustrates the switching network of FIG. 8 in somewhat more detail; and
FIG. 9A is a table of various valve openings for FIG. 9.
DESCRIPTION OF THE PREFERRED EMBODIMENT In FIG. 1 there is illustrated an elongated vessel 10 on station above the water bottom 12. The vessel 10 may be in the form of an elongated barge and includes a full compliment of production equipment 14 such as high and low-pressure separators, free-water knockouts, treaters etc. situated on the open deck, and additionally includes a plurality of storage tanks 16 connected to receive the output from the production equipment 14'for storing treated crude oil.
Positioned near thebow 18 and within the boundaries of the vessel is a well 20 extending from the deck 21 to the bottom 22 of vessel 10. Positioned within the well 20 is a swivel means in the form of mooring swivel 24 extending from the deck to below the water surface and held in position by mooring means in the form of a plurality of anchor chains 26 (only two are shown) firmly secured to the water bottom 12 so that the vesselwill weathervane about the swivel 24 to maintain the bow portion headed into the waves and wind. For those conditions where wind and sea are not in agreement, thrust units 28 are provided at the stern of the vessel 10 and are operable to maintain the vessel on the most favorable heading.
It is preferable that crews living quarters 29 be established forward of the swivel 24 since the vessel always weathervanes into'the wind and the bow may serve as the place of last refuge for the crew in the event of fire.
A more detailed, cross-sectional view of the swivel and part of the vessel, is illustrated in FIG. 2.
The swivel 24 has a large diameter tube 25 situated within the well 20 and an upper flange portion forming a swivel platform 47.
The swivel 24 is rotatably supported by a plurality of roller units 50 extending from the bottom of swivel platform 47 to a circular track 51 on the deck 21. The swivel 24 is additionally restrained laterally by a set of upper roller units 53 extending between the tube 25 and track 54, and a plurality of lower roller'units 57 extending between the tube 25 and track 58.
Each anchor chain 26 extends up through a flange 60 at the bottom of the swivel 24, through the swivel platform 47 and secured thereto at respective securing points 62.
The hose assembly 32 includes at least a pair of fluid carrying lines in the form of production line 65 and circulation line 66. A third line 67 is a control line andmay include power conveying means for actuating valves at the underwater well such means being, for example, hydraulic pneumatic or electrical. Alternatively the control line 67 may be eliminated and the valves controlled automatically in response to coded acoustic signals transmitted through the water medium. The lines 65, 66 and 67 are held together as a unit by means of a spacer 69 such spacers-being distributed along the length of the assembly. Bouyant materials 70, also disposed along the length of the assembly prevent the assembly from possibly dragging on the water bottom.
The three lines 65, 66 and 67 pass up through a relatively small diameter vertical tube 73 within the swivel 24, and are disconnectable by means of a hose assembly connector 75. Production line 65 and circulation line 66 pass up through a support 77 positioned on the swivel platform 47.
In operation when the wells are producing, and only two are shown for clarity, well fluid, for example from well 36 passes up the production line 65 through a first or master valve 100, into connecting pipe 102, through a second or wing valve 104 and into a centrally located vertical header 107, a header being a tube, chamber or similar structure to which a bank or series of tubes or other connections are joined to permit fluid flow. Suitable flow control units such as chokes may be included but are not shown herein.
Well fluid from well 37 passes up the production line 84 to the master valve 110, through connecting pipe 112 and wing valve 114 into the header 107, In a similar fashion well fluid from all of the other wells in the field flow into header 107 and the comingled well fluid iscarried to the production equipment by production hose 116 connected to the header 107 by means of a rotary pipe joint 1 19,
In order to efficiently produce an oilfield it is necessary to have information about how much oil and gas and water each individual well is producing and at what pressures. On the vessel there is provided a test and metering station which includes a metering separator where the components of the well fluid are separated and individually metered. Accordingly means are provided for selectively controlling fluid flow in individual ones of the fluid lines to place individual wells on test. This means, in the embodiment of FIG. 2, includes an annual header 122 concentrically disposed about header 107, and a plurality of valves for connecting the production line from each well to the annular header. Since the annular header 122 is utilized in test operations it will herein be termed the test header. With respect to well 36 there is provided valve 124 which when open will divert the flow from connecting pipe 102 into connecting pipe 126 and test header 122. During such operation wing valve 104 would normally be closed.
With respect to well 37, fluid from production line 84 may be diverted from connecting pipe 112 by opening valve 129 so that produced fluid may enter the test header 122 by way of connecting pipe 130. Wing valve 114 would normally be closed while the remaining wing valves from the other assemblies would be open such that during testing operations well fluid from only one well is diverted into the test header 122.
The test header 122 communicates with a testing station in a manner to be hereinafter described.
There are many maintenance operations which an oil well may require during its life, such as cleaning paraffin out of the flow line and tubing string in the well, bailing sand, changing various chokes in the system, bottom hole pressure surveys and the installation and removal of production control and safety devices, to name a few. There has been developed a technique for performing these operations by means of various tools which are pumped down through the flow line and returned after accomplishing the desired operation. The present invention provides for the full utilization of this technique by the provision of means for selectively inserting a tool string of one or more units into individual one of the fluid lines, in conjunction with'means for delivering and returning the tool string from the sell. For this purpose, and in the embodiment of FIG. 2, there is provided a plurality of valves on the swivel platform for individually controlling fluid flow in the circulation lines. By way of example and with respect to well 36, the circulation line 66 includes a first or master valve 134, and a second or wing valve 136. When both of these valves are open, and a third or swabbing valve 138 is closed, fluid communication is established between circulation line 66 and a second annular header l40'herein termed the circula tion header and concentrically disposed about the header 107.
With respect to well 37, fluid flow in circulation line is controlled by a first valve 142 and a second valve 144 both of which are operable when open to communicate fluid with the circulation header 140.
Since the valves at the underwater well may be controlled in a number of different ways including acoustic means, for clarity no particular connections are illustrated for the control lines 67 and 86.
Insertion of a pump down tool string into a fluid line such as production line 65 may be accomplished with the provision of a lubricator 42. The tool string is inserted into the lubricator 42 which is connected to the production line such as by flange connection 146. Pressure is then applied at the top of the lubricator while swabbing valve 148 and master valve are open to send the tool string out of the lubricator and past the level of wing valve 104. If the tool string to be inserted is very long, the valving means at the underwater wellhead can be closed and the entire length of flow line used as a lubricator. By proper connection and selective operation of swabbing valves 138, 148, 150 and 151, tool strings may be inserted into respective fluid lines 66, 65, 84 and 85.
Means, including guide or track extending around the periphery of the swivel platform 47, are provided for connecting the test header 122 and circulation header 140 to certain equipment on the vessel. Such connections are better illustrated in FIG. 3 which is a plan view of the swivel platform 47 of FIG. 2 with the valves and certain other equipment omitted for clarity. Positioned on the periphery of swivel platform 47 is a first connecting means such as a rotary pipe joint 159 and a second connecting means such as rotary pipe joint 161. Test header 122 is connected to the rotary pipe joint 159 by means of fluid conveying conduit 163 and circulation header 140 is connected to rotary pipe joint 161 by means of fluid convening conduit 164.
First and second reels and 171 on the vessel deck have flexible hoses 173 and 174 coiled thereon and connected respectively to rotary pipe joints 159 and 161. The other end of hose 173 is connected through a rotary pipe joint to fluid conduit 176 and the other end of flexible hose 174 is connected through a rotary pipe joint to fluid conduit 177. As the vessel pivots about the swivel, for example in FIG. 3 if swivel platform 47 relatively moves counterclockwise, hoses 173 and 174 will be pulled from their respective reels I70 and 171 and will be placed in the track means 155. Another view of this operation is illustrated in FIG. 5. When the swivel platform 47 relatively moves in a clockwise direction reels 170 and 171 will take up the slack of the hoses 173 and 174. This arrangement provides fluid communication, and prevents entanglement as the vessel rotates about the swivel. The relative rotation may be for a full turn or more depending upon the length of hose 173 or 174.
Alternatively, and as illustrated in the plan view of FIG. 5,
additional counterpart equipment may be provided on the,
bow side of the swivel platform 47. The additional system components are shown in dotted line and have primed reference numerals. As a typical operation let it be assumed that rotary pipe joint 159 is connected to reel 170 and rotary pipe joint 161 is connected to reel 171. Should the swivel rotate a half turn, the rotary pipe joints 159 and 161 may be connected up to respective reels 170 and 171' by means of suitable valving and connection means not illustrated. Thereafter another half turn in the same direction will bring the rotary pipe joints 159 and 161 into a position to be again connected to reels 170 and 171.
In FIG. 6 there is illustrated a flow diagram for the underwater well 36, Those components previously described in other figures have been given the same reference numeral. At the upper portion of the figure are the components illustrated in FIG. 2 for selective control of the underwater well 36. At the lower portion of the figure there is illustrated a pile structure 188 secured to the water bottom 12 and which supports a hose assembly connector 190. The production line 65 extending from the connector 190 over to the well 36 may be in the fonn of steel tubing having curvatures 192 of sufficient radius, for example 5 feet, to enable passage of long tool trains and would lie on the bottom 12.
The circulation line 66 on the bottom may similarly be of steel tubing with curvatures 193 to enable tool train passage.
The underwater well 36 includes a Christmas tree 193 with the production line 65 being connected with the production string 195 by means of wing valve 197 and master valve 198. Circulation line 66 is connected to the circulation string 200 by means of wing valve 202 and master valve 203.
During operation of the well it may be necessary to perform a certain operation such as the removal of a valve 106 in the production string. The apparatus of the present invention allows such maintenance operation to be performed by the use of conventional pump down tool techniques and to this end reference is now made to FIG. 7.
FIG. 7 illustrates a flow diagram and components already described have been given the same reference numeral.
Onboard apparatus for testing and servicing the various wells includes a test separator and metering station 210 and a pump and metering station 212 in conjunction with a plurality of valves 214 through 217.
If it is desired to test the well fluid of underwater well 36, valves 124 and 214 are open. Well fluid then proceeds from production string 195 to production line 65, through valve 124 into the test header 122, out of the test header and into fluid line 176 by way of the rotary pipe joint 159 and flexible hose 173 wound on reel 170. From fluid conduit 176 the fluid passes through valve 214 and into the test separator and metering station 210. The well fluid as it emerges from the well is at very high pressures, for example thousands of p.s.i. and the test separator at station 210 reduces the pressure to atmospheric. After suitable testing the quiescent crude is provided to a tank 16 and if it is desired to test other wells, valve 124 may be closed and a similar wing valve associated with another well may be opened to deliver that wells fluid to station 210.
If it is desired to test the well through circulation line 66, valves 136 and 217 may be opened to establish fluid flow from the circulation line 66 into circulation header 140 through rotary pipe joint 161 and flexible hose 174 to the reel 171 and fluid conduit 177 and into the test station 210 through valve 217.
For maintenance operation where it is required to send a tool string down into the production string 195, the arrangement of FIG. 7 may be utilized as shown in FIG. 7A, which for clarity, shows only those conduits and valves involved in the operation.
After performance of the necessary operation, the tool string is returned as illustrated in FIG. 7B. Pumping station 212 pumps the quiescent crude down the circulation line 66 by the path including valve 216, fluid conduit 177, flexible hose 174, rotary pipe joint l6l', circulation header and valve 136. Fluid displaced ahead of the tool string in production line 65 is returned to the testing station 210 by the path including valve 124, test header 122, rotary pipe joint 159, flexible hose 173, fluid conduit 176 and valve 214.
The pumping station 212 includes metering means for determining the approximate position of the tool in the line 65, since there is a direct relationship between its position and the quantity of quiescent crude pumped.
In addition to test and tool service, the circulating line 66 could also be used to provide gas to the wells for artificial lift for which purpose there is illustrated a gas lift system 220.
Unloading of the vessel 10 can be accomplished by having a tanker come alongside, special fendering and mooring winches being provided aboard the vessel 10 to prevent metalto-metal contact between the hulls and to maintain good control over the tanker. Alternatively, the tanker could approach from astern and tie to a single mooring line from the stern of the vessel 10 the oil being transferred from storage tanks 16 through a floating hose; if the tanker were to go astern slowly on its engine the two hulls need never come in contact. However, for reason of the security of the loading hoses, some shipmasters might prefer the former method which provides for the tanker to be well secured alongside the vessel 10. For those cases where proper handling of the tanker requires that it have ballast water in some of its tanks, pollution of the sea can be avoided by discharging this dirty ballast into special tanks on the vessel 10, which could take the time between unloadingsto treat this water for discharge into the sea. It should be noted that thrust units 28 would be available for assistance in the mooring operation.
A typical vessel 10 may have a length in the order of 600 feet with a beam or width of 80 feet and a depth from top deck to the bottom of the vessel of 50 feet. The storage capacity of such vessel may be 300,000 barrels and approximately 16 wells may be serviced by means of the arrangement described. Larger vessels and swivels may accommodate a larger number of wells however there is a point at which practical limitations on the size of the swivel will limit the number of wells which can be accommodated within it. For a greater number of wells, the arrangement of FIG. 8 may be utilized.
In FIG. 8 there is illustrated the swivel 24 within the vessel 10 at the surface and depending from the swivel 24 and extending toward the water bottom 12 is a plurality of flexible fluid conveying conduits 224, 225 and 226 with the flexible conduit 224 being a production line, flexible conduit 225 being a test and tool line, and flexible conduit 226 being the circulation line. These flexible conduits are held in spaced relationship by means of spacers 228 with buoyant material 229 as previously described.
Positioned on the water bottom 12 is a gathering station 236 which includes a landing base 238 concreted in position within a pile 240 in the water bottom.
Mating with the landing base 238 and being detachably secured thereto is a manifold means 242 which includes a carrier unit 244 having a guide pipe 245 for guiding the unit into its position on the landing base 238. The manifold means 242 is connected to the landing base 238 by a plurality of detachable connectors 248.
The manifold means 242 includes header 252 in addition to a plurality of test and tool lines 225a to 225n having respective valves 254a to 254n. Each line 225a to 225;: is connected with the header 252 by means of respective branch lines 2580 to 258n having respective valves 459a to 259n. The test and tool lines 225a to 225n are selectively connectable to test and tool line 225 through a switching network 261. The manifold means also includes a plurality of circulation lines 226a to 226a having respective valves 260a to 260n which connect the lines 2260 to 226n with the circulation line 226.
When the carrier unit 244 is in mating engagement with the landing base 238, connections are provided between lines 225a to 2251 and respective lines 225a to 225n' which carry the well fluid from respective wells of which two, 264 and 265, are illustrated. Connection is also made between lines 226a to 226:: and lines 226a to 226n' which constitute the circulation lines for the individual wells. The fluid lines extending from the base 238 are suitably valved to allow for detachment of the manifold means 242.
The comingled production lines 224, the test and tool line 225 and the circulation line 226 extend from the manifold means 242 up through the swivel 24 in the vessel 10 and at the swivel platform 47 rotary pipe joint 268 connected to the comingled production line 224 connects the well production with the vessel-carried production equipment by way of the hose 270. Means are provided for connecting the test and tool line 225 and circulation line 226 with the pumping and the test stations as previously described. The means may include respective pipe connections to the periphery of the swivel platform 47 and thereafter to a hose and reel arrangement as previously described. Alternatively, suitable valving means may be supplied to these lines at the swivel platform 47 and thereafter the lines may be directly connected with a pumping and test station for those situations where relatively little swivel action takes place or for those instances where some degree of twisting of lines may be tolerated.
Assuming that means are provided for control of the valves illustrated at the gathering station 236, a typical operation will now be described. Valves 254a to 254n in the test and tool lines and valves 260a to 26011 in the circulation line are closed; all other valves are open. Well fluid from the various wells flow up the respective lines 225a to 225n' and into the header 252 through respective valved branch lines 258a to 258n. The comingled fluids then travel up the flexible line 224, through the swivel and to the production equipment. If it is now desired to test a certain well, for example well 264, valve 259a in the branch line 258a is closed and valve 254a in line 225a is opened so that the well fluid from well 264 travels up the test and tool line 225, through the swivel 24 and to a test station as described previously with respect to FIG. 7. Subsequent to the test, valve 259a is again opened and valve 254a is closed.
If a maintenance operation is to be performed at one of the wells, for example well 265, and such operation requires the use of a tool string, such tool string may be inserted in the test line 225 at the swivel platform 47. Valve 259k in branch line 258b is closed and valve 254b in line 225b as well as valve 26Gb in circulation line 226b is opened. By means of the arrangement illustrated in FIG. 7A (except for the annular headers which would not be needed), the tool string is pumped down the test and tool line 225, enters the switching network 261 where it is directed-to line 225b and thereafter to the well 265. Upon completion of the maintenance operation the tool string may be returned'by the method illustrated in FIG. 7B, the'tool string passing up through the switching network 261 and after its recovery at the swivel platform 47 the valves may be returned to their respectively normally operating conditions.
The switching network 261 is operative upon proper command from the surface, such as by hydraulic, pneumatic, electric or acoustically encoded signal activation to switch a tool string in test line 225 from the vessel 10 to any selected one of a number of underwater sells connected to the gathering station 236. A typical switching network may include various branch lines with fluidic switching such as illustrated in FIG. 9 wherein a switching network for controlling nine wells is shown. The switching network of FIG. 9 includes a plurality of fluidic switches 280 to 283 each having an input line, three output lines and two control lines. The lines for each fluidic switch are labeled accordingly and operation is such that if a high-pressure fluid is supplied to the first control line, the tool will be forced over to the third output line. If high-pressure fluid is supplied to the second control line the tool will be forced over to the first output line and if high-pressure fluid is supplied to both the first and second control lines (or simultaneously not supplied to both lines) then the tool string will pass straight through to the second output line. In order to supply the high-pressure fluid to the various fluidic switches there is provided a control unit 286 which includes a source of high-pressure fluid and which has eight outputs controlled by eight valves designated V1 to V8.
A tool string at the input of fluidic switch 280 may be directed to any one of the nine wells by selective opening of one or more of the valves V1 to V8. If the tool string is to be sent to well 1, valves V3 and V8 are opened whereby the tool string at fluidic switch 280 is forced by the high-pressure fluid in the second control line over to the first output line as is the case in fluidic switch 281. For servicing well 5, all of the valves are closed (or all of the valves may be opened) such that the tool exits from fluidic'switch 280 at the second output with a similar exit from fluidic switch 282. The table of FIG. 9A designates the particular valve or valves which are to be opened in order to service the designated wells.
The principle demonstrated in-FIG. 9 may be expanded such that many more than nine wells may be serviced. Fluidic switching may also be accomplished with a fluidic switch having one input and two outputs and two control lines however many more fluidic switches would be required.
For the accommodation of a greater number of wells a plurality of gathering stations may be provided in conjunction with a header arrangement on the swivel 24. The arrangement would include a first header for valved connection with all the comingled production lines, a second header for valved connection with all the circulation lines, and a third header for valved connection with all the test and tool lines. Fluid connection with the pumping test and metering stations would be similar to that previously illustrated.
Although the present invention has been described with a certain degree of particularity it should be understood that the present disclosure has been made by way of example and that modifications and variations of the present invention are made possible in the light of the above teachings.
I claim as my invention:
1. Offshore oil production apparatus comprising a. an elongated vessel having a well extending vertically therethrough to below the vessels waterline;
b. swivel means positioned within said well, and including a swivel platform at the upper portion thereof;
0. means for mooring said swivel means to the bottom of a body of water; oil production equipment carried by said vessel; said vessel including storage tanks for receiving the output of said oil producing equipment, a test separator and metering station, and a pumping station; a plurality of flexible fluid carrying lines for connection to a plurality of underwater oil wells, said flexible fluid carrying lines extending up through said swivel means to said swivel platform; means for inserting tool strings into selected one of said flexible fluid carrying lines; flow control means i. for selectively connecting individual ones of said flexible fluid carrying lines with said test separator and metering station for placing individual ones of said underwater wells on test, and ii. for selectively connecting individual one of said flexible fluid carrying lines with said pumping station for delivering and returning tool strings inserted into selected flexible fluid carrying lines;
I I. first header means for comingling produced well fluid from said underwater oil wells; and
J. first conduit means for carrying said comingled well fluid to said oil production equipment.
2. Apparatus according to claim 1 wherein:
A. the swivel means includes a relatively large diameter vertical tube depending from the swivel platform; and
B. a plurality of relatively smaller diameter vertical tubes extending vertically within said large diameter tube;
C. at least pairs of flexible fluid carrying lines extending to the swivel platform through respective ones of said smaller diameter tubes.
3. Apparatus according to claim 1 wherein:
A. for each underwater well there is provided at least two flexible fluid carrying lines, constituting a production line and a circulation line.
2. Apparatus according to claim 3 wherein:
A. each production line and each circulation line of each underwater well extends up through the swivel means; and which includes B. a test header and a circulation header positioned on the swivel platform;
C. a first plurality of valves respectively connecting each production line with said test header; and
D. a second plurality of valves respectively connecting each circulation line with said circulation header.
5. Apparatus according to claim 3 which includes:
A. at least one underwater gathering station;
B. valve connections at said gathering station for combining the production lines of a plurality of underwater wells;
C. other valve connections at said gathering station for combining the circulation lines-of a plurality of underwater wells;
D. means connecting the combined production lines with a first one of the flexible fluid carrying lines extending up the swivel means and for connecting the combined circulation lines with a second one of the flexible fluid carrying lines extending up the swivel means.
6. Apparatus according to claim 5 which includes:
A. a switching matrix at said gathering station for diverting tool strings into a selected one of the production lines.
7. Apparatus according to claim 5 wherein:
A. the swivel means is located near the bow of the vessel,
and which includes,
B. crews living quarters situated between the swivel means and said bow.
8. Apparatus according to claim 1 wherein:
A. the first header means is centrally located on the swivel platform, and which includes B. a rotary pipe joint connecting the first conduit means to the first header means.
9. Apparatus according to claim 8 wherein:
A. the production header and circulation header are concentrically disposed about the first header.
10. Apparatus according to claim 1 wherein:
A. the pumping station pumps crude oil from one of the storage tanks.
1 1. Apparatus according to claim 10 wherein:
A. the pumping station includes metering means for metering the quantity of the crude oil pumped, for determining the approximate location of a tool string in a selected one of the flexible fluid carrying lines.
12. Apparatus according to claim 1 which includes:
A. second and third header means;
B. selected ones of said flexible fluid carrying lines being connected to said second header means;
C. other ones of said flexible fluid carrying lines being connected to said third header means;
D. a pair of connection means respectively connected to said second and third header means;
E. a pair of hose reels each operable to wind and unwind carried hose; F. one end of the hoses from said pair of hose reels being connectable with respective ones of said pair of connection means;
G. means for selectively connecting the other end of said hoses to the test separator and metering station and the pumping station.
13. Apparatus according to claim 12 wherein:
A. the pair. of connection means are disposed on the periphery of the swivel platform; and which includes B. a guide on said periphery of the swivel platform for receiving respective hoses from the hose reel when the vessel and swivel means relatively rotate.
Claims (13)
1. Offshore oil production apparatus comprising a. an elongated vessel having a well extending vertically therethrough to below the vessel''s waterline; b. swivel means positioned within said well, and including a swivel platform at the upper portion thereof; c. means for mooring said swivel means to the bottom of a body of water; d. oil production equipment carried by said vessel; e. said vessel including storage tanks for receiving the output of said oil producing equipment, a test separator and metering station, and a pumping station; f. a plurality of flexible fluid carrying lines for connection to a plurality of underwater oil wells, said flexible fluid carrying lines extending up through said swivel means to said swivel platform; g. means for inserting tool strings into selected one of said flexible fluid carrying lines; h. flow control means i. for selectively connecting individual ones of said flexible fluid carrying lines with said test separator and metering station for placing individual ones of said underwater wells on test, and ii. for selectively connecting individual one of said flexible fluid carrying lines with said pumping station for delivering and returning tool strings inserted into selected flexible fluid carrying lines; I. first header means for comingling produced well fluid from said underwater oil wells; and J. first conduit means for carrying said comingled well fluid to said oil production equipment.
2. Apparatus according to claim 3 wherein: A. each production line and each circulation line of each underwater well extends up through the swivel means; and which includes B. a test header and a circulation header positioned on the swivel platform; C. a first plurality of valves respectively connecting each production line with said test header; and D. a second plurality of valves respectively connecting each circulation line with said circulation header.
2. Apparatus according to claim 1 wherein: A. the swivel means includes a relatively large diameter vertical tube depending from the swivel platform; and B. a plurality of relatively smaller diameter vertical tubes extending vertically within said large diameter tube; C. at least pairs of flexible fluid carrying lines extending to the swivel platform through respective ones of said smaller diameter tubes.
3. Apparatus according to claim 1 wherein: A. for each underwater well there is provided at least two flexible fluid carrying lines, constituting a produCtion line and a circulation line.
5. Apparatus according to claim 3 which includes: A. at least one underwater gathering station; B. valve connections at said gathering station for combining the production lines of a plurality of underwater wells; C. other valve connections at said gathering station for combining the circulation lines of a plurality of underwater wells; D. means connecting the combined production lines with a first one of the flexible fluid carrying lines extending up the swivel means and for connecting the combined circulation lines with a second one of the flexible fluid carrying lines extending up the swivel means.
6. Apparatus according to claim 5 which includes: A. a switching matrix at said gathering station for diverting tool strings into a selected one of the production lines.
7. Apparatus according to claim 5 wherein: A. the swivel means is located near the bow of the vessel, and which includes, B. crew''s living quarters situated between the swivel means and said bow.
8. Apparatus according to claim 1 wherein: A. the first header means is centrally located on the swivel platform, and which includes B. a rotary pipe joint connecting the first conduit means to the first header means.
9. Apparatus according to claim 8 wherein: A. the production header and circulation header are concentrically disposed about the first header.
10. Apparatus according to claim 1 wherein: A. the pumping station pumps crude oil from one of the storage tanks.
11. Apparatus according to claim 10 wherein: A. the pumping station includes metering means for metering the quantity of the crude oil pumped, for determining the approximate location of a tool string in a selected one of the flexible fluid carrying lines.
12. Apparatus according to claim 1 which includes: A. second and third header means; B. selected ones of said flexible fluid carrying lines being connected to said second header means; C. other ones of said flexible fluid carrying lines being connected to said third header means; D. a pair of connection means respectively connected to said second and third header means; E. a pair of hose reels each operable to wind and unwind carried hose; F. one end of the hoses from said pair of hose reels being connectable with respective ones of said pair of connection means; G. means for selectively connecting the other end of said hoses to the test separator and metering station and the pumping station.
13. Apparatus according to claim 12 wherein: A. the pair of connection means are disposed on the periphery of the swivel platform; and which includes B. a guide on said periphery of the swivel platform for receiving respective hoses from the hose reel when the vessel and swivel means relatively rotate.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US87535069A | 1969-11-10 | 1969-11-10 |
Publications (1)
Publication Number | Publication Date |
---|---|
US3602302A true US3602302A (en) | 1971-08-31 |
Family
ID=25365651
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US875350A Expired - Lifetime US3602302A (en) | 1969-11-10 | 1969-11-10 | Oil production system |
Country Status (1)
Country | Link |
---|---|
US (1) | US3602302A (en) |
Cited By (88)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3760875A (en) * | 1970-06-29 | 1973-09-25 | Shell Oil Co | Floating structure with rotatable templet for connecting guide lines thereto |
US3774562A (en) * | 1972-06-12 | 1973-11-27 | Global Marine Inc | 360{20 {11 rotary anchoring system with differential drive capability |
FR2413536A1 (en) * | 1977-12-30 | 1979-07-27 | Inst Francais Du Petrole | ANCHORING AND TRANSFER STATION FOR THE PRODUCTION OF OIL OFFSHORE OIL |
FR2417005A1 (en) * | 1978-02-14 | 1979-09-07 | Inst Francais Du Petrole | NEW ANCHORING AND TRANSFER STATION FOR THE PRODUCTION OF OIL OFFSHORE OIL |
US4281716A (en) * | 1979-08-13 | 1981-08-04 | Standard Oil Company (Indiana) | Flexible workover riser system |
FR2483004A1 (en) * | 1979-08-09 | 1981-11-27 | Halliburton Co | DISCHARGE PIPING SYSTEM |
FR2533879A1 (en) * | 1982-06-22 | 1984-04-06 | Mobil Oil Corp | SEA TREATMENT VESSEL AND METHOD OF OPERATING THIS VESSEL TO RECEIVE OIL AND / OR GAS PRODUCTION FROM AN UNDERWATER WELL |
FR2569223A1 (en) * | 1984-08-20 | 1986-02-21 | Blohm Voss Ag | DISTRIBUTION STATION FOR THE CONNECTION OF SEVERAL DRILLING HOLES PRESENT IN THE MARINE BOTTOM |
FR2573173A1 (en) * | 1984-11-12 | 1986-05-16 | Coflexip | DEVICE FOR TRANSFERRING FLUID BETWEEN A FIXED STRUCTURE AND A MOBILE STRUCTURE IN ROTATION USING AT LEAST ONE FLEXIBLE DRIVE |
EP0186969A1 (en) * | 1984-12-24 | 1986-07-09 | Mobil Oil Corporation | Rotating fluid manifold |
US4606727A (en) * | 1983-12-07 | 1986-08-19 | Blohm & Voss Ag | Anchoring arrangement for a tanker, including a fluid transfer system |
US4616700A (en) * | 1984-09-18 | 1986-10-14 | Hydril Company | Automatic well test system and method |
US4698038A (en) * | 1984-10-17 | 1987-10-06 | Key Ocean Services, Inc. | Vessel mooring system and method for its installation |
US4701143A (en) * | 1984-10-17 | 1987-10-20 | Key Ocean Services, Inc. | Vessel mooring system and method for its installation |
GB2192040A (en) * | 1986-06-23 | 1987-12-31 | Gec Elliott Mech Handling | Transferring fluids or electricity between relatively rotating bodies |
US4735267A (en) * | 1985-03-11 | 1988-04-05 | Shell Oil Company | Flexible production riser assembly and installation method |
EP0371669A1 (en) * | 1988-11-28 | 1990-06-06 | Golar-Nor Offshore A.S. | A system for transferring fluids from a piping system in a ship's hull to a turning device, and vice versa |
US4972907A (en) * | 1985-10-24 | 1990-11-27 | Shell Offshore Inc. | Method of conducting well operations from a moveable floating platform |
US5018578A (en) * | 1990-08-06 | 1991-05-28 | Halliburton Company | Method of arresting hydraulic fracture propagation |
US5135327A (en) * | 1991-05-02 | 1992-08-04 | Conoco Inc. | Sluice method to take TLP to heave-restrained mode |
US5147148A (en) * | 1991-05-02 | 1992-09-15 | Conoco Inc. | Heave-restrained platform and drilling system |
US5150987A (en) * | 1991-05-02 | 1992-09-29 | Conoco Inc. | Method for installing riser/tendon for heave-restrained platform |
US5330293A (en) * | 1993-02-26 | 1994-07-19 | Conoco Inc. | Floating production and storage facility |
US5749758A (en) * | 1994-02-02 | 1998-05-12 | Den Norske Stats Oljeselskap A.S., I & K Patent | Vessel for production and/or loading/unloading and transport of hydrocarbons from offshore fields, and/or for carrying out well operations |
WO1998031919A1 (en) * | 1997-01-16 | 1998-07-23 | Jens Korsgaard | Method and apparatus for producing and shipping hydrocarbons offshore |
US5885028A (en) * | 1996-12-10 | 1999-03-23 | American Oilfield Divers, Inc. | Floating systems and method for storing produced fluids recovered from oil and gas wells |
WO1999038763A1 (en) * | 1998-01-28 | 1999-08-05 | Kværner Oil & Gas A.S | An arrangement for a drilling/production vessel with geostationary anchoring |
US6012530A (en) * | 1997-01-16 | 2000-01-11 | Korsgaard; Jens | Method and apparatus for producing and shipping hydrocarbons offshore |
US6019174A (en) * | 1997-01-16 | 2000-02-01 | Korsgaard; Jens | Method and apparatus for producing and shipping hydrocarbons offshore |
US6047781A (en) * | 1996-05-03 | 2000-04-11 | Transocean Offshore Inc. | Multi-activity offshore exploration and/or development drilling method and apparatus |
EP1097287A1 (en) * | 1998-07-10 | 2001-05-09 | Fmc Corporation | Floating spar for supporting production risers |
US6390733B1 (en) * | 1999-07-02 | 2002-05-21 | Imodco, Inc. | Simplified storage barge and method of operation |
WO2002070336A1 (en) * | 2001-03-06 | 2002-09-12 | Fmc Technologies, Inc. | Radial bearing arrangement and method for installation |
US20030141111A1 (en) * | 2000-08-01 | 2003-07-31 | Giancarlo Pia | Drilling method |
US6601649B2 (en) * | 2001-05-01 | 2003-08-05 | Drillmar, Inc. | Multipurpose unit with multipurpose tower and method for tendering with a semisubmersible |
US6640901B1 (en) * | 1999-09-10 | 2003-11-04 | Alpha Thames Ltd. | Retrievable module and operating method suitable for a seabed processing system |
US20040011530A1 (en) * | 2002-03-26 | 2004-01-22 | Felthager Michael J. | Long stroking tool |
US20040240946A1 (en) * | 2001-10-22 | 2004-12-02 | Ope Technology, Llc | Floating platform with separators and storage tanks for LNG and liquid gas forms of hydrocarbons |
US20040251025A1 (en) * | 2003-01-30 | 2004-12-16 | Giroux Richard L. | Single-direction cementing plug |
US20040258484A1 (en) * | 2001-10-22 | 2004-12-23 | Ope Technology, Llc | Floating platform with storage tanks for compressed gas and/or hydrate forms of hydrocarbons |
EP1496297A2 (en) * | 2003-07-11 | 2005-01-12 | Weatherford/Lamb, Inc. | Vessel for well intervention |
US6938697B2 (en) | 2001-05-17 | 2005-09-06 | Weatherford/Lamb, Inc. | Apparatus and methods for tubular makeup interlock |
US20050211440A1 (en) * | 2004-03-25 | 2005-09-29 | Johannes Lanfermeijer | Offshore nitrogen production and injection |
US6968899B1 (en) * | 1999-10-27 | 2005-11-29 | Single Buoy Moorings Inc. | Drilling-workover vessel having a drill string extending through at least one swivel |
US20060004593A1 (en) * | 2004-06-30 | 2006-01-05 | Devon Energy Corporation | Method and system for gathering, transporting and marketing offshore oil and gas |
US6994176B2 (en) | 2002-07-29 | 2006-02-07 | Weatherford/Lamb, Inc. | Adjustable rotating guides for spider or elevator |
US7004264B2 (en) | 2002-03-16 | 2006-02-28 | Weatherford/Lamb, Inc. | Bore lining and drilling |
US7013997B2 (en) | 1994-10-14 | 2006-03-21 | Weatherford/Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7036610B1 (en) | 1994-10-14 | 2006-05-02 | Weatherford / Lamb, Inc. | Apparatus and method for completing oil and gas wells |
US7040420B2 (en) | 1994-10-14 | 2006-05-09 | Weatherford/Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US20060108120A1 (en) * | 2004-11-22 | 2006-05-25 | Energy Equipment Corporation | Well production and multi-purpose intervention access hub |
US7083005B2 (en) | 2002-12-13 | 2006-08-01 | Weatherford/Lamb, Inc. | Apparatus and method of drilling with casing |
US7090023B2 (en) | 2002-10-11 | 2006-08-15 | Weatherford/Lamb, Inc. | Apparatus and methods for drilling with casing |
US7090021B2 (en) | 1998-08-24 | 2006-08-15 | Bernd-Georg Pietras | Apparatus for connecting tublars using a top drive |
US7096982B2 (en) | 2003-02-27 | 2006-08-29 | Weatherford/Lamb, Inc. | Drill shoe |
US7100713B2 (en) | 2000-04-28 | 2006-09-05 | Weatherford/Lamb, Inc. | Expandable apparatus for drift and reaming borehole |
US7100710B2 (en) | 1994-10-14 | 2006-09-05 | Weatherford/Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7108084B2 (en) | 1994-10-14 | 2006-09-19 | Weatherford/Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7128161B2 (en) | 1998-12-24 | 2006-10-31 | Weatherford/Lamb, Inc. | Apparatus and methods for facilitating the connection of tubulars using a top drive |
US7131505B2 (en) | 2002-12-30 | 2006-11-07 | Weatherford/Lamb, Inc. | Drilling with concentric strings of casing |
US7137454B2 (en) | 1998-07-22 | 2006-11-21 | Weatherford/Lamb, Inc. | Apparatus for facilitating the connection of tubulars using a top drive |
US7140445B2 (en) | 1997-09-02 | 2006-11-28 | Weatherford/Lamb, Inc. | Method and apparatus for drilling with casing |
US7147068B2 (en) | 1994-10-14 | 2006-12-12 | Weatherford / Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7165634B2 (en) | 1994-10-14 | 2007-01-23 | Weatherford/Lamb, Inc. | Method and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7191840B2 (en) | 2003-03-05 | 2007-03-20 | Weatherford/Lamb, Inc. | Casing running and drilling system |
US7213656B2 (en) | 1998-12-24 | 2007-05-08 | Weatherford/Lamb, Inc. | Apparatus and method for facilitating the connection of tubulars using a top drive |
US7216727B2 (en) | 1999-12-22 | 2007-05-15 | Weatherford/Lamb, Inc. | Drilling bit for drilling while running casing |
US7219744B2 (en) | 1998-08-24 | 2007-05-22 | Weatherford/Lamb, Inc. | Method and apparatus for connecting tubulars using a top drive |
US7284617B2 (en) | 2004-05-20 | 2007-10-23 | Weatherford/Lamb, Inc. | Casing running head |
US7325610B2 (en) | 2000-04-17 | 2008-02-05 | Weatherford/Lamb, Inc. | Methods and apparatus for handling and drilling with tubulars or casing |
US20080135256A1 (en) * | 2006-12-06 | 2008-06-12 | Chevron U.S.A. Inc. | Subsea Manifold System |
US20080140337A1 (en) * | 2006-12-06 | 2008-06-12 | Chevron U.S.A. Inc. | Overpressure protection device |
US20080138159A1 (en) * | 2006-12-06 | 2008-06-12 | Chevron U.S.A. Inc. | Marine Riser System |
US20080264642A1 (en) * | 2007-04-24 | 2008-10-30 | Horton Technologies, Llc | Subsea Well Control System and Method |
US7509722B2 (en) | 1997-09-02 | 2009-03-31 | Weatherford/Lamb, Inc. | Positioning and spinning device |
US7669662B2 (en) | 1998-08-24 | 2010-03-02 | Weatherford/Lamb, Inc. | Casing feeder |
US7694744B2 (en) | 2005-01-12 | 2010-04-13 | Weatherford/Lamb, Inc. | One-position fill-up and circulating tool and method |
US20100098498A1 (en) * | 2008-10-16 | 2010-04-22 | Gavin Humphreys | Anchor system for offshore dynamically positioned drilling platform |
US7712523B2 (en) | 2000-04-17 | 2010-05-11 | Weatherford/Lamb, Inc. | Top drive casing system |
US7757759B2 (en) | 2006-04-27 | 2010-07-20 | Weatherford/Lamb, Inc. | Torque sub for use with top drive |
US7793725B2 (en) | 2006-12-06 | 2010-09-14 | Chevron U.S.A. Inc. | Method for preventing overpressure |
US7802636B2 (en) | 2007-02-23 | 2010-09-28 | Atwood Oceanics, Inc. | Simultaneous tubular handling system and method |
US7845418B2 (en) | 2005-01-18 | 2010-12-07 | Weatherford/Lamb, Inc. | Top drive torque booster |
US7874352B2 (en) | 2003-03-05 | 2011-01-25 | Weatherford/Lamb, Inc. | Apparatus for gripping a tubular on a drilling rig |
US7882902B2 (en) | 2006-11-17 | 2011-02-08 | Weatherford/Lamb, Inc. | Top drive interlock |
US7958938B2 (en) | 2004-05-03 | 2011-06-14 | Exxonmobil Upstream Research Company | System and vessel for supporting offshore fields |
USRE42877E1 (en) | 2003-02-07 | 2011-11-01 | Weatherford/Lamb, Inc. | Methods and apparatus for wellbore construction and completion |
US8215888B2 (en) | 2009-10-16 | 2012-07-10 | Friede Goldman United, Ltd. | Cartridge tubular handling system |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2699321A (en) * | 1949-06-21 | 1955-01-11 | Fred N Nelson | Deepwater oil drilling and storage craft |
US3111692A (en) * | 1960-12-14 | 1963-11-26 | Shell Oil Co | Floating production platform |
US3279404A (en) * | 1963-12-20 | 1966-10-18 | Offshore Co | Floating mooring system |
US3335690A (en) * | 1965-04-27 | 1967-08-15 | Shell Oil Co | Floating storage unit for a fluid |
US3407768A (en) * | 1967-01-11 | 1968-10-29 | Continental Oil Co | Offshore storage, mooring and loading facility |
US3440671A (en) * | 1966-04-12 | 1969-04-29 | Robert Smulders | Floating device for loading or unloading a ship in open water |
US3472032A (en) * | 1967-12-01 | 1969-10-14 | Pan American Petroleum Corp | Production and storage system for offshore oil wells |
US3525312A (en) * | 1967-10-06 | 1970-08-25 | Exxon Production Research Co | Storage or similar vessel |
-
1969
- 1969-11-10 US US875350A patent/US3602302A/en not_active Expired - Lifetime
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2699321A (en) * | 1949-06-21 | 1955-01-11 | Fred N Nelson | Deepwater oil drilling and storage craft |
US3111692A (en) * | 1960-12-14 | 1963-11-26 | Shell Oil Co | Floating production platform |
US3279404A (en) * | 1963-12-20 | 1966-10-18 | Offshore Co | Floating mooring system |
US3335690A (en) * | 1965-04-27 | 1967-08-15 | Shell Oil Co | Floating storage unit for a fluid |
US3440671A (en) * | 1966-04-12 | 1969-04-29 | Robert Smulders | Floating device for loading or unloading a ship in open water |
US3407768A (en) * | 1967-01-11 | 1968-10-29 | Continental Oil Co | Offshore storage, mooring and loading facility |
US3525312A (en) * | 1967-10-06 | 1970-08-25 | Exxon Production Research Co | Storage or similar vessel |
US3472032A (en) * | 1967-12-01 | 1969-10-14 | Pan American Petroleum Corp | Production and storage system for offshore oil wells |
Cited By (140)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3760875A (en) * | 1970-06-29 | 1973-09-25 | Shell Oil Co | Floating structure with rotatable templet for connecting guide lines thereto |
US3774562A (en) * | 1972-06-12 | 1973-11-27 | Global Marine Inc | 360{20 {11 rotary anchoring system with differential drive capability |
FR2413536A1 (en) * | 1977-12-30 | 1979-07-27 | Inst Francais Du Petrole | ANCHORING AND TRANSFER STATION FOR THE PRODUCTION OF OIL OFFSHORE OIL |
FR2417005A1 (en) * | 1978-02-14 | 1979-09-07 | Inst Francais Du Petrole | NEW ANCHORING AND TRANSFER STATION FOR THE PRODUCTION OF OIL OFFSHORE OIL |
FR2483004A1 (en) * | 1979-08-09 | 1981-11-27 | Halliburton Co | DISCHARGE PIPING SYSTEM |
US4339002A (en) * | 1979-08-09 | 1982-07-13 | Halliburton Company | Sea buoy discharge manifold system |
US4281716A (en) * | 1979-08-13 | 1981-08-04 | Standard Oil Company (Indiana) | Flexible workover riser system |
FR2533879A1 (en) * | 1982-06-22 | 1984-04-06 | Mobil Oil Corp | SEA TREATMENT VESSEL AND METHOD OF OPERATING THIS VESSEL TO RECEIVE OIL AND / OR GAS PRODUCTION FROM AN UNDERWATER WELL |
US4448568A (en) * | 1982-06-22 | 1984-05-15 | Mobil Oil Corporation | Marine surface facility work station for subsea equipment handling |
US4606727A (en) * | 1983-12-07 | 1986-08-19 | Blohm & Voss Ag | Anchoring arrangement for a tanker, including a fluid transfer system |
US4765378A (en) * | 1984-08-20 | 1988-08-23 | Jurgen Engelskirchen | Valve station for interconnecting boreholes in a seabed |
GB2163403A (en) * | 1984-08-20 | 1986-02-26 | Blohm Voss Ag | Off-shore valve station |
FR2569223A1 (en) * | 1984-08-20 | 1986-02-21 | Blohm Voss Ag | DISTRIBUTION STATION FOR THE CONNECTION OF SEVERAL DRILLING HOLES PRESENT IN THE MARINE BOTTOM |
DE3430628A1 (en) * | 1984-08-20 | 1986-02-27 | Blohm + Voss Ag, 2000 Hamburg | VALVE STATION FOR CONNECTING SEVERAL DRILL HOLES ON THE SEA BASE |
US4616700A (en) * | 1984-09-18 | 1986-10-14 | Hydril Company | Automatic well test system and method |
US4701143A (en) * | 1984-10-17 | 1987-10-20 | Key Ocean Services, Inc. | Vessel mooring system and method for its installation |
US4698038A (en) * | 1984-10-17 | 1987-10-06 | Key Ocean Services, Inc. | Vessel mooring system and method for its installation |
US4690181A (en) * | 1984-11-12 | 1987-09-01 | Coflexip | Apparatus to transfer fluid between a fixed structure and a rotatable structure by using at least one flexible conduit |
EP0182705A1 (en) * | 1984-11-12 | 1986-05-28 | Coflexip | Device for fluid transport between a fixed structure and a rotating structure using at least one flexible conduit |
FR2573173A1 (en) * | 1984-11-12 | 1986-05-16 | Coflexip | DEVICE FOR TRANSFERRING FLUID BETWEEN A FIXED STRUCTURE AND A MOBILE STRUCTURE IN ROTATION USING AT LEAST ONE FLEXIBLE DRIVE |
EP0186969A1 (en) * | 1984-12-24 | 1986-07-09 | Mobil Oil Corporation | Rotating fluid manifold |
US4735267A (en) * | 1985-03-11 | 1988-04-05 | Shell Oil Company | Flexible production riser assembly and installation method |
US4972907A (en) * | 1985-10-24 | 1990-11-27 | Shell Offshore Inc. | Method of conducting well operations from a moveable floating platform |
GB2192040A (en) * | 1986-06-23 | 1987-12-31 | Gec Elliott Mech Handling | Transferring fluids or electricity between relatively rotating bodies |
EP0371669A1 (en) * | 1988-11-28 | 1990-06-06 | Golar-Nor Offshore A.S. | A system for transferring fluids from a piping system in a ship's hull to a turning device, and vice versa |
US5113778A (en) * | 1988-11-28 | 1992-05-19 | Golar-Nor Offshore As | System for transferring fluids from a piping system in a ship's hull to a turning device, and vice versa |
US5018578A (en) * | 1990-08-06 | 1991-05-28 | Halliburton Company | Method of arresting hydraulic fracture propagation |
US5135327A (en) * | 1991-05-02 | 1992-08-04 | Conoco Inc. | Sluice method to take TLP to heave-restrained mode |
US5147148A (en) * | 1991-05-02 | 1992-09-15 | Conoco Inc. | Heave-restrained platform and drilling system |
US5150987A (en) * | 1991-05-02 | 1992-09-29 | Conoco Inc. | Method for installing riser/tendon for heave-restrained platform |
US5330293A (en) * | 1993-02-26 | 1994-07-19 | Conoco Inc. | Floating production and storage facility |
US5749758A (en) * | 1994-02-02 | 1998-05-12 | Den Norske Stats Oljeselskap A.S., I & K Patent | Vessel for production and/or loading/unloading and transport of hydrocarbons from offshore fields, and/or for carrying out well operations |
US7013997B2 (en) | 1994-10-14 | 2006-03-21 | Weatherford/Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7147068B2 (en) | 1994-10-14 | 2006-12-12 | Weatherford / Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7108084B2 (en) | 1994-10-14 | 2006-09-19 | Weatherford/Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7165634B2 (en) | 1994-10-14 | 2007-01-23 | Weatherford/Lamb, Inc. | Method and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7100710B2 (en) | 1994-10-14 | 2006-09-05 | Weatherford/Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7040420B2 (en) | 1994-10-14 | 2006-05-09 | Weatherford/Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7036610B1 (en) | 1994-10-14 | 2006-05-02 | Weatherford / Lamb, Inc. | Apparatus and method for completing oil and gas wells |
US6047781A (en) * | 1996-05-03 | 2000-04-11 | Transocean Offshore Inc. | Multi-activity offshore exploration and/or development drilling method and apparatus |
US6056071A (en) * | 1996-05-03 | 2000-05-02 | Transocean Offshore Inc. | Multi-activity offshore exploration and/or development drilling method and apparatus |
US6068069A (en) * | 1996-05-03 | 2000-05-30 | Transocean Offshore Inc. | Multi-activity offshore exploration and/or development drilling method and apparatus |
US6085851A (en) * | 1996-05-03 | 2000-07-11 | Transocean Offshore Inc. | Multi-activity offshore exploration and/or development drill method and apparatus |
US5885028A (en) * | 1996-12-10 | 1999-03-23 | American Oilfield Divers, Inc. | Floating systems and method for storing produced fluids recovered from oil and gas wells |
US6012530A (en) * | 1997-01-16 | 2000-01-11 | Korsgaard; Jens | Method and apparatus for producing and shipping hydrocarbons offshore |
US6230809B1 (en) | 1997-01-16 | 2001-05-15 | Jens Korsgaard | Method and apparatus for producing and shipping hydrocarbons offshore |
WO1998031919A1 (en) * | 1997-01-16 | 1998-07-23 | Jens Korsgaard | Method and apparatus for producing and shipping hydrocarbons offshore |
GB2335406B (en) * | 1997-01-16 | 2001-07-04 | Jens Korsgaard | Method and apparatus for producing and shipping hydrocarbons offshore |
GB2335406A (en) * | 1997-01-16 | 1999-09-22 | Jens Korsgaard | Method and apparatus for producing and shipping hydrocarbons offshore |
US6019174A (en) * | 1997-01-16 | 2000-02-01 | Korsgaard; Jens | Method and apparatus for producing and shipping hydrocarbons offshore |
US7509722B2 (en) | 1997-09-02 | 2009-03-31 | Weatherford/Lamb, Inc. | Positioning and spinning device |
US7140445B2 (en) | 1997-09-02 | 2006-11-28 | Weatherford/Lamb, Inc. | Method and apparatus for drilling with casing |
GB2349613A (en) * | 1998-01-28 | 2000-11-08 | Kvaerner Oil & Gas As | An arrangement for a drilling/production vessel with geostationary anchoring |
WO1999038763A1 (en) * | 1998-01-28 | 1999-08-05 | Kværner Oil & Gas A.S | An arrangement for a drilling/production vessel with geostationary anchoring |
GB2349613B (en) * | 1998-01-28 | 2001-09-19 | Kvaerner Oil & Gas As | An arrangement for a drilling/production vessel with geostationary anchoring |
EP1097287A1 (en) * | 1998-07-10 | 2001-05-09 | Fmc Corporation | Floating spar for supporting production risers |
EP1097287A4 (en) * | 1998-07-10 | 2002-03-27 | Fmc Corp | Floating spar for supporting production risers |
US6336421B1 (en) * | 1998-07-10 | 2002-01-08 | Fmc Corporation | Floating spar for supporting production risers |
US7137454B2 (en) | 1998-07-22 | 2006-11-21 | Weatherford/Lamb, Inc. | Apparatus for facilitating the connection of tubulars using a top drive |
US7665531B2 (en) | 1998-07-22 | 2010-02-23 | Weatherford/Lamb, Inc. | Apparatus for facilitating the connection of tubulars using a top drive |
US7219744B2 (en) | 1998-08-24 | 2007-05-22 | Weatherford/Lamb, Inc. | Method and apparatus for connecting tubulars using a top drive |
US7353880B2 (en) | 1998-08-24 | 2008-04-08 | Weatherford/Lamb, Inc. | Method and apparatus for connecting tubulars using a top drive |
US7451826B2 (en) | 1998-08-24 | 2008-11-18 | Weatherford/Lamb, Inc. | Apparatus for connecting tubulars using a top drive |
US7513300B2 (en) | 1998-08-24 | 2009-04-07 | Weatherford/Lamb, Inc. | Casing running and drilling system |
US7090021B2 (en) | 1998-08-24 | 2006-08-15 | Bernd-Georg Pietras | Apparatus for connecting tublars using a top drive |
US7669662B2 (en) | 1998-08-24 | 2010-03-02 | Weatherford/Lamb, Inc. | Casing feeder |
US7213656B2 (en) | 1998-12-24 | 2007-05-08 | Weatherford/Lamb, Inc. | Apparatus and method for facilitating the connection of tubulars using a top drive |
US7128161B2 (en) | 1998-12-24 | 2006-10-31 | Weatherford/Lamb, Inc. | Apparatus and methods for facilitating the connection of tubulars using a top drive |
US6390733B1 (en) * | 1999-07-02 | 2002-05-21 | Imodco, Inc. | Simplified storage barge and method of operation |
US6640901B1 (en) * | 1999-09-10 | 2003-11-04 | Alpha Thames Ltd. | Retrievable module and operating method suitable for a seabed processing system |
US6968899B1 (en) * | 1999-10-27 | 2005-11-29 | Single Buoy Moorings Inc. | Drilling-workover vessel having a drill string extending through at least one swivel |
US7216727B2 (en) | 1999-12-22 | 2007-05-15 | Weatherford/Lamb, Inc. | Drilling bit for drilling while running casing |
US7918273B2 (en) | 2000-04-17 | 2011-04-05 | Weatherford/Lamb, Inc. | Top drive casing system |
US7793719B2 (en) | 2000-04-17 | 2010-09-14 | Weatherford/Lamb, Inc. | Top drive casing system |
US7654325B2 (en) | 2000-04-17 | 2010-02-02 | Weatherford/Lamb, Inc. | Methods and apparatus for handling and drilling with tubulars or casing |
US7712523B2 (en) | 2000-04-17 | 2010-05-11 | Weatherford/Lamb, Inc. | Top drive casing system |
US7325610B2 (en) | 2000-04-17 | 2008-02-05 | Weatherford/Lamb, Inc. | Methods and apparatus for handling and drilling with tubulars or casing |
US7100713B2 (en) | 2000-04-28 | 2006-09-05 | Weatherford/Lamb, Inc. | Expandable apparatus for drift and reaming borehole |
US7093675B2 (en) | 2000-08-01 | 2006-08-22 | Weatherford/Lamb, Inc. | Drilling method |
US20030141111A1 (en) * | 2000-08-01 | 2003-07-31 | Giancarlo Pia | Drilling method |
US6477974B2 (en) * | 2001-03-06 | 2002-11-12 | Fmc Technologies, Inc. | Radial bearing arrangement and method for installation |
WO2002070336A1 (en) * | 2001-03-06 | 2002-09-12 | Fmc Technologies, Inc. | Radial bearing arrangement and method for installation |
US6601649B2 (en) * | 2001-05-01 | 2003-08-05 | Drillmar, Inc. | Multipurpose unit with multipurpose tower and method for tendering with a semisubmersible |
US7073598B2 (en) | 2001-05-17 | 2006-07-11 | Weatherford/Lamb, Inc. | Apparatus and methods for tubular makeup interlock |
US6938697B2 (en) | 2001-05-17 | 2005-09-06 | Weatherford/Lamb, Inc. | Apparatus and methods for tubular makeup interlock |
US7281587B2 (en) | 2001-05-17 | 2007-10-16 | Weatherford/Lamb, Inc. | Apparatus and methods for tubular makeup interlock |
US8517090B2 (en) | 2001-05-17 | 2013-08-27 | Weatherford/Lamb, Inc. | Apparatus and methods for tubular makeup interlock |
US7896084B2 (en) | 2001-05-17 | 2011-03-01 | Weatherford/Lamb, Inc. | Apparatus and methods for tubular makeup interlock |
US20040258484A1 (en) * | 2001-10-22 | 2004-12-23 | Ope Technology, Llc | Floating platform with storage tanks for compressed gas and/or hydrate forms of hydrocarbons |
US20040240946A1 (en) * | 2001-10-22 | 2004-12-02 | Ope Technology, Llc | Floating platform with separators and storage tanks for LNG and liquid gas forms of hydrocarbons |
US7004264B2 (en) | 2002-03-16 | 2006-02-28 | Weatherford/Lamb, Inc. | Bore lining and drilling |
US20040011530A1 (en) * | 2002-03-26 | 2004-01-22 | Felthager Michael J. | Long stroking tool |
US7448456B2 (en) | 2002-07-29 | 2008-11-11 | Weatherford/Lamb, Inc. | Adjustable rotating guides for spider or elevator |
US6994176B2 (en) | 2002-07-29 | 2006-02-07 | Weatherford/Lamb, Inc. | Adjustable rotating guides for spider or elevator |
US7090023B2 (en) | 2002-10-11 | 2006-08-15 | Weatherford/Lamb, Inc. | Apparatus and methods for drilling with casing |
US7083005B2 (en) | 2002-12-13 | 2006-08-01 | Weatherford/Lamb, Inc. | Apparatus and method of drilling with casing |
US7131505B2 (en) | 2002-12-30 | 2006-11-07 | Weatherford/Lamb, Inc. | Drilling with concentric strings of casing |
US20040251025A1 (en) * | 2003-01-30 | 2004-12-16 | Giroux Richard L. | Single-direction cementing plug |
US7128154B2 (en) | 2003-01-30 | 2006-10-31 | Weatherford/Lamb, Inc. | Single-direction cementing plug |
USRE42877E1 (en) | 2003-02-07 | 2011-11-01 | Weatherford/Lamb, Inc. | Methods and apparatus for wellbore construction and completion |
US7096982B2 (en) | 2003-02-27 | 2006-08-29 | Weatherford/Lamb, Inc. | Drill shoe |
US7874352B2 (en) | 2003-03-05 | 2011-01-25 | Weatherford/Lamb, Inc. | Apparatus for gripping a tubular on a drilling rig |
US7191840B2 (en) | 2003-03-05 | 2007-03-20 | Weatherford/Lamb, Inc. | Casing running and drilling system |
US20110174483A1 (en) * | 2003-03-05 | 2011-07-21 | Odell Ii Albert C | Apparatus for gripping a tubular on a drilling rig |
US8567512B2 (en) | 2003-03-05 | 2013-10-29 | Weatherford/Lamb, Inc. | Apparatus for gripping a tubular on a drilling rig |
US10138690B2 (en) | 2003-03-05 | 2018-11-27 | Weatherford Technology Holdings, Llc | Apparatus for gripping a tubular on a drilling rig |
EP1496297A3 (en) * | 2003-07-11 | 2005-05-11 | Weatherford/Lamb, Inc. | Vessel for well intervention |
EP1496297A2 (en) * | 2003-07-11 | 2005-01-12 | Weatherford/Lamb, Inc. | Vessel for well intervention |
AU2004203054B2 (en) * | 2003-07-11 | 2007-09-13 | Weatherford Technology Holdings, Llc | Vessel for well intervention |
US7650944B1 (en) | 2003-07-11 | 2010-01-26 | Weatherford/Lamb, Inc. | Vessel for well intervention |
US20050211440A1 (en) * | 2004-03-25 | 2005-09-29 | Johannes Lanfermeijer | Offshore nitrogen production and injection |
WO2005096792A3 (en) * | 2004-03-25 | 2006-05-11 | Single Buoy Moorings | Offshore nitrogen production and injection |
WO2005096792A2 (en) * | 2004-03-25 | 2005-10-20 | Single Buoy Moorings, Inc. | Offshore nitrogen production and injection |
US7958938B2 (en) | 2004-05-03 | 2011-06-14 | Exxonmobil Upstream Research Company | System and vessel for supporting offshore fields |
US7284617B2 (en) | 2004-05-20 | 2007-10-23 | Weatherford/Lamb, Inc. | Casing running head |
US20060004593A1 (en) * | 2004-06-30 | 2006-01-05 | Devon Energy Corporation | Method and system for gathering, transporting and marketing offshore oil and gas |
US20060108120A1 (en) * | 2004-11-22 | 2006-05-25 | Energy Equipment Corporation | Well production and multi-purpose intervention access hub |
US7219740B2 (en) * | 2004-11-22 | 2007-05-22 | Energy Equipment Corporation | Well production and multi-purpose intervention access hub |
US7694744B2 (en) | 2005-01-12 | 2010-04-13 | Weatherford/Lamb, Inc. | One-position fill-up and circulating tool and method |
US7845418B2 (en) | 2005-01-18 | 2010-12-07 | Weatherford/Lamb, Inc. | Top drive torque booster |
US7757759B2 (en) | 2006-04-27 | 2010-07-20 | Weatherford/Lamb, Inc. | Torque sub for use with top drive |
US7882902B2 (en) | 2006-11-17 | 2011-02-08 | Weatherford/Lamb, Inc. | Top drive interlock |
US7793726B2 (en) | 2006-12-06 | 2010-09-14 | Chevron U.S.A. Inc. | Marine riser system |
US7798233B2 (en) * | 2006-12-06 | 2010-09-21 | Chevron U.S.A. Inc. | Overpressure protection device |
US7793725B2 (en) | 2006-12-06 | 2010-09-14 | Chevron U.S.A. Inc. | Method for preventing overpressure |
US7793724B2 (en) | 2006-12-06 | 2010-09-14 | Chevron U.S.A Inc. | Subsea manifold system |
US20080135256A1 (en) * | 2006-12-06 | 2008-06-12 | Chevron U.S.A. Inc. | Subsea Manifold System |
US20080140337A1 (en) * | 2006-12-06 | 2008-06-12 | Chevron U.S.A. Inc. | Overpressure protection device |
US20080138159A1 (en) * | 2006-12-06 | 2008-06-12 | Chevron U.S.A. Inc. | Marine Riser System |
US8584773B2 (en) | 2007-02-23 | 2013-11-19 | Atwood Oceanics, Inc. | Simultaneous tubular handling system and method |
US9410385B2 (en) | 2007-02-23 | 2016-08-09 | Friede Goldman United, Ltd. | Simultaneous tubular handling system |
US10612323B2 (en) | 2007-02-23 | 2020-04-07 | Friede & Goldman United B.V. | Simultaneous tubular handling system |
US8186455B2 (en) | 2007-02-23 | 2012-05-29 | Atwood Oceanics, Inc. | Simultaneous tubular handling system and method |
US7802636B2 (en) | 2007-02-23 | 2010-09-28 | Atwood Oceanics, Inc. | Simultaneous tubular handling system and method |
US7921919B2 (en) * | 2007-04-24 | 2011-04-12 | Horton Technologies, Llc | Subsea well control system and method |
US20080264642A1 (en) * | 2007-04-24 | 2008-10-30 | Horton Technologies, Llc | Subsea Well Control System and Method |
US20100098498A1 (en) * | 2008-10-16 | 2010-04-22 | Gavin Humphreys | Anchor system for offshore dynamically positioned drilling platform |
US8215888B2 (en) | 2009-10-16 | 2012-07-10 | Friede Goldman United, Ltd. | Cartridge tubular handling system |
US9476265B2 (en) | 2009-10-16 | 2016-10-25 | Friede Goldman United, Ltd. | Trolley apparatus |
US8696289B2 (en) | 2009-10-16 | 2014-04-15 | Friede Goldman United, Ltd. | Cartridge tubular handling system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3602302A (en) | Oil production system | |
CA1196232A (en) | Offshore process vessel and a method of operating same to receive oil and/or gas production from a subsea well | |
US7628224B2 (en) | Shallow/intermediate water multipurpose floating platform for arctic environments | |
US5433273A (en) | Method and apparatus for production of subsea hydrocarbon formations | |
CN102756794B (en) | Semi-submersible type production platform of reservoir oil positioned below water surface | |
US8142108B2 (en) | Riser installation method from an offshore production unit | |
EP0387076B1 (en) | Offshore oil production system | |
US6453838B1 (en) | Turret-less floating production ship | |
US4436048A (en) | Rotary transfer subsystems and tensioning assemblies for a process vessel | |
US6336419B1 (en) | Floating structure | |
RU2144611C1 (en) | Vessel for recovery or transportation of hydrocarbons from sea deposits and method for oil filling through loading hose | |
CA2325133A1 (en) | Submerged pipeline manifold for offloading mooring buoy and method of installation | |
JPH02501561A (en) | Offshore oil well floating production system and drilling vessel | |
US6682265B1 (en) | Method of establishing and/or operating a bore well in a seabed and a drilling vessel for use in connection therewith | |
Leverette | Design of the Disconnectable Buoy Turret Mooring for the Turritella FPSO | |
Faldini et al. | FDS2 and Castorone: A reply for the deepwater forthcoming vision | |
Miller et al. | The Heidrun field-marine operations | |
Mahoney | Balmoral: conception to production | |
Drawe III et al. | Technical and economic considerations in developing offshore oil and gas prospects using floating production systems | |
Millmaker et al. | The Challenges of Lufeng 22-1 Development | |
Dwyer | Marine Pipe Laying Methods | |
Lentz et al. | Conceptual Design of a Turret-Moored Production System (TUMOPS) | |
Pike | Economic benefits of FPSO construction and deployment in the Gulf of Mexico | |
O'Connor | The Development Of A Floating Storage Unit For The Alba Project | |
English | ABOUT THE ONE-ATMOSPHERE MANIFOLD CENTER |