CN103490506A - Method for testing telecommand response time through substation measuring and control device telecommand quantity testing system - Google Patents

Method for testing telecommand response time through substation measuring and control device telecommand quantity testing system Download PDF

Info

Publication number
CN103490506A
CN103490506A CN201310156096.6A CN201310156096A CN103490506A CN 103490506 A CN103490506 A CN 103490506A CN 201310156096 A CN201310156096 A CN 201310156096A CN 103490506 A CN103490506 A CN 103490506A
Authority
CN
China
Prior art keywords
remote signalling
control device
substation
measure
electric substation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310156096.6A
Other languages
Chinese (zh)
Other versions
CN103490506B (en
Inventor
开圣武
夏友斌
赵武
黄晟
张爱萍
蒋桐生
田文芃
朱明�
林其友
潘文虎
宋铭敏
章莉
陈绍范
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Wuhu Power Supply Co of State Grid Anhui Electric Power Co Ltd
Original Assignee
Wuhu Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhu Power Supply Co of State Grid Anhui Electric Power Co Ltd filed Critical Wuhu Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority to CN201310156096.6A priority Critical patent/CN103490506B/en
Publication of CN103490506A publication Critical patent/CN103490506A/en
Application granted granted Critical
Publication of CN103490506B publication Critical patent/CN103490506B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a method for testing the telecommand response time through a substation measuring and control device telecommand quantity testing system. The substation measuring and control device telecommand quantity testing system is provided with a satellite time service device which outputs time ticks to all automatic devices inside a substation, the satellite time service device is provided with a plurality of timing pulse units, and meanwhile outputs a PPD space contact signal to measuring and control devices in the automatic devices, and after telecommand units of the measuring and control devices receive pulses, SOE displacement information generated by the measuring and control devices is transmitted to a substation computer monitoring system and outputted to the upper-level automatic system outside the substation through a telecontrol communication device. The substation measuring and control device telecommand quantity testing system is simple in structure, low in building cost and convenient to extend. Scientific and effective automatic testing on telecommand quantity correlation technical indexes and function timing can be carried out on measuring and control devices which are different in voltage class and produced by different manufacturers at home and abroad, the substation computer monitoring system and the upper-level system such as a centralized control station automatic system or all-level power grid dispatching automatic master station systems.

Description

A kind of method of testing of electric substation's measure and control device remote signalling measurement test system to the remote signalling response time of utilizing
Technical field
The present invention relates to a kind of method of testing of electric substation's measure and control device remote signalling measurement test system to the remote signalling response time of utilizing.
Background technology
Along with the continuous expansion of China's electrical network scale, current China electrical network has entered into the new stage of Kua great district, ultra high voltage, alternating current-direct current series-parallel connection operation, and it is more complicated that Regulation becomes.For guarantee the power supply quality and reliability and the economy of electric power system, grid dispatching center must be grasped the ruuning situation of whole system real-time and accurately, analyzed in time and made correct judgement and decision-making, take urgent measure in case of necessity, process emergent accident and abnormal conditions, to guarantee the safe, reliable and effective supply of electric power.
The power system network structure is increasingly sophisticated, the control difficulty continues to increase, control centres at different levels require more information accurately, in order to grasp in time the ruuning situation of electrical network and electric substation, therefore to the automation system for the power network dispatching reliability of operation, require also more and more higher.And to realize power network schedule automation, at first need a large amount of real time execution parameters of acquisition and processing and status signal.
Current in secondary equipment in power system, measure alternating voltage and electric current, direct voltage, temperature with measure and control device widely, collection signal, carry out deciliter control to circuit breaker and disconnecting link etc.In whole automated system, measure and control device is a very important subsystem, it has born the collection of remote signalling, remote measurement initial data, born guidance command the reliable task of execution in addition accepted, complete Data Management Analysis simultaneously, the work such as sequence of events recording are the core apparatus of Synthetic Automation System of Transformer Substation wall.The remote signalling amount (quantity of state) wherein gathered has directly reflected the operation conditions of power system operating mode and the station electricity consumption of electric substation's alternating current-direct current and auxiliary equipment thereof etc., it is one of the most basic in automation system for the power network dispatching, most important function, special requirement accurately, reliably, in real time, are inscribed but often exist the remote signalling mistake to send out in reality and leak question.Wherein the remote signalling mistake is sent out the normal operation of not only disturbing whole dispatch automated system, but also have a strong impact on accident alarming and to the judgement of electric network fault and to the correct processing of power grid accident, so relevant power industry and national technical standard have strict requirement to the action accuracy of remote signalling with the time that is sent to main website, in " DL/T 550-94 regional power grid scheduling automation function standard ", require area power dispatching automation system.
Remote signalling accuracy (year) basic index is >=99%, the response time that requires the switching value signal to input to picture disply in " DL/T 5149-2001 220 ~ 500kV electric substation Computer Monitoring System Design technical regulation " is not more than the 2S(response time and refers to and send information from wall I/O unit, complete the time till picture to station level), " GB/T 13730-2002 area power dispatching automation system " claimed condition quantitative change position is transferred to main station time≤3s.
But current automation system for the power network dispatching at different levels lacks effectively statistics and means of testing to These parameters, in addition to remote signalling displacement test, the test of telemetry system time accuracy, stand in SOE, stand between SOE, the excessive remote signalling displacement of system disposal ability (remote signalling storm) these indexs and function also be difficult to carry out normality, the reliable test.(journal of SOE self-explanatory characters' part, the moment that the recording status amount changes and sequencing.)
Therefore how research sets up a set of electric substation measure and control device remote signalling amount timing automatic test macro on existing Synthetic Automation System of Transformer Substation technical merit basis, be used for measure and control device, electric substation's computer supervisory control system and upper level system thereof (Masterstation Automation System or power network schedule automation main station system) are carried out normalization, automation, the test of standardized remote signalling action accuracy, the test of system remote signalling response time, remote signalling displacement test, the test of telemetry system time accuracy, the SOE instation test, test between the SOE station, the excessive remote signalling displacement of system disposal ability (remote signalling storm) test, find in time said apparatus and system and main plant stand telecontrol channel tissue, communication protocol, the weak link of traffic rate, carry out targetedly malfunction elimination and rectification, improve dispatching automation Operation, Administration and Maintenance level, become an urgent demand of present stage dispatching automation work.
Summary of the invention
Technical problem to be solved by this invention is to realize a kind of electric substation measure and control device remote signalling amount timing automatic test macro, can be to measure and control device, electric substation's computer supervisory control system and upper level system thereof are carried out normalization, automation, standardized remote signalling amount index of correlation and functional test, remote signalling displacement information is recorded in verifiable on-the-spot remote signalling displacement roll-call action character and a distant place, receive sequence of events recording SOE tripartite consistency, investigate the measure and control device unimpeded accuracy of communicating by letter with distant place automated system, find in time said apparatus and system and the configuration of main factory station data storehouse point table, the telecontrol channel tissue, communication protocol, the weak link of traffic rate, carry out targetedly malfunction elimination and rectification, improve work quality and efficiency.
To achieve these goals, the technical solution used in the present invention is:
The measure and control device remote signalling of a kind of electric substation measures test system, this system be provided with to all automation equipments output in an electric substation to the time signal the satellite time transfer device, described satellite time transfer device is provided with the multicircuit time pulse unit, and the idle contact of output day pulse simultaneously signal is to the measure and control device in described automation equipment, described measure and control device remote signalling unit is sent to electric substation's computer supervisory control system by the SOE displacement information of its generation after receiving this pulse, and the output of the upper level automated system outside electric substation by remote control communication equipment.
Described idle contact signal is the pulse signal that the pulse duration regularly sent every day is 1S.
A kind of method of testing of electric substation's measure and control device remote signalling measurement test system to remote signalling action accuracy of utilizing, when the satellite time transfer device sends the idle contact signal to the N platform measure and control device in electric substation, N platform measure and control device sends 2N SOE signal, and the remote signalling obtained action accuracy is correct operation number of times in the SOE signal and the percentage of 2N.
A kind of method of the method for testing of remote signalling action accuracy to device fault detect in system of utilizing, if the accuracy that this electric substation's computer supervisory control system remote signalling action accuracy receives higher than the upper level system, may there be the error code phenomenon in electric substation toward the teletransmission passage of upper level automated system, can carry out hidden troubles removing for passage; Leak to send out a day pulse signal as the fruit part measure and control device and cause remote signalling action accuracy to descend, there is fault in the abnormal or measure and control device of the remote signalling power work of this part measure and control device with communicating by letter of station level system.
A kind of method of testing of electric substation's measure and control device remote signalling measurement test system to the remote signalling response time of utilizing, send pulse at the satellite time transfer device and constantly start the stopwatch counting, to adding up electric substation's computer supervisory control system and upper level system, detect or show that the moment of SOE signal is the remote signalling response time.
A kind of method of testing of electric substation's measure and control device remote signalling measurement test system to time accuracy of utilizing, measure and control device will produce a SOE displacement information after receiving the pulse action information that the satellite time transfer device sends, and stamp time mark, this electric substation's computer supervisory control system and upper level system thereof also all can be stamped mark operate time according to the system time of oneself after receiving these remote signalling displacement information, by check concrete SOE displacement information can judge corresponding measure and control device to the time precision have error, can verify this electric substation's computer supervisory control system and each own time accuracy of upper level system thereof according to the remote signalling displacement information corresponding with certain SOE displacement information.
A kind of method of electric substation's measure and control device remote signalling measurement test system to the interior SOE test of standing of utilizing, it is characterized in that: utilize the satellite time transfer device to input a day pulse idle contact signal to two or more measure and control devices, thereby whether test electric substation's computer supervisory control system and upper level system thereof can correctly identify two and above remote signalling action event in same electric substation simultaneously.
A kind of method of electric substation's measure and control device remote signalling measurement test system to SOE test between station of utilizing, a plurality of electric substations satellite time transfer device is sent to day pulse action constantly unified, the precedence that the different SOE of the electric substation information that receive according to Masterstation Automation System or its power network schedule automation main station system at the same level arrive detects two and above action event in different electric substations, obtains communication mode and the quality of processing response time of electric substation and upper level automated system.
A kind of method of electric substation's measure and control device remote signalling measurement test system to the test of remote signalling storm of utilizing, it is characterized in that: according to standby of concrete measure and control device remote signalling unit, scene quantity, every measure and control device accesses a road or sky, some roads pulse signal intake, the total remote signalling amount of day pulse is expanded to meet the quantity of remote signalling storm test, thereby test tested electric substation computer supervisory control system and upper level system thereof the disposal ability to a large amount of remote signalling displacement in scene event.
A kind of method of electric substation's measure and control device remote signalling measurement test system to remote signalling displacement test of utilizing, every day, timing automatic produced one-off and involution remote signalling displacement to the measure and control device of electric substation's all accesses day pulse idle contact, record remote signalling displacement information, reception sequence of events recording SOE tripartite consistency by verifying the on-the-spot remote signalling displacement action character of calling the roll with a distant place, thereby record the measure and control device unimpeded accuracy of communicating by letter with the upper level automated system.
The invention has the advantages that the present invention builds simply, construction cost is low, expansion is convenient, can all carry out scientific and effective remote signalling amount Specifications, the test of function timing automatic to measure and control device, electric substation's computer supervisory control system and the upper level system thereof (Masterstation Automation System or power network schedule automation main station system at different levels) of different electric pressures, domestic and international different manufacturers.
The accompanying drawing explanation
Below the content of every width accompanying drawing expression in specification of the present invention and the mark in figure are briefly described:
Fig. 1 is that the measure and control device remote signalling of a kind of electric substation measures the test system structured flowchart.
Embodiment
Known referring to Fig. 1, full station synchro system unified time that this system is based on electric substation's installation is the satellite time transfer device, this device reception Beidou satellite navigation system or gps satellite are as the external time reference signal, hereinafter take GPS as example explanation, gps satellite synchronised clock can realize entirely the standing operation monitoring of each system under the unified time benchmark and the accident analysis after accident.Electric substation is provided with a large amount of automation equipments, these equipment comprise measure and control device, fault oscillograph, microcomputer protecting device, the station level main frame, remote control communication equipment etc., the precision clock synchronizing signal that the output of satellite time transfer device is provided by GPS is to all automation equipments of electric substation, unified electric substation, the time reference of control centre, after electric power system is broken down, improved the time accuracy of SOE, for analyzing circuit breaker and protection, the sequencing of automatic safety device action provides strong evidence, for electricity net safety stable monitoring and controlling system has been created good technical conditions.Existing gps satellite clock system support firmly to the time (impulse contact 1PPS etc.), soft to the time (serial ports message), coding to the time (IRIG-B, DCF77) and network N TP to the time, meet domestic and international distinct device to the time interface requirement.
Some road 1PPD idle contact (pulse duration 1S by the output of a plurality of days pulse units (1PPD) of Substation Time Synchronous System, sending of day pulse 1PPD can be set constantly) signal, receive the stand-by state amount input terminal of every measure and control device in station by the general control cable, at the sky pulse action arranged constantly, within all days, the pulse idle contact all will produce a displacement signal, make each measure and control device that receives this signal produce respectively a SOE displacement information, and on deliver to this computer supervisory control system and by remote control communication equipment the upper level system to electric substation outside export, relatively each measurement and control unit to the time difference of same event response and each receiving system to the SOE disposal ability with a collection of event, be used for measure and control device, electric substation's computer supervisory control system and upper level system thereof are carried out the test of remote signalling action accuracy, the test of system remote signalling response time, remote signalling displacement test, the test of telemetry system time accuracy, the SOE instation test, test between the SOE station, the excessive remote signalling displacement of system disposal ability (remote signalling storm) test.Wherein the upper level automated system comprises Masterstation Automation System and power network schedule automation main station system.
Concrete method of testing is as follows:
The test of remote signalling action accuracy:
The not high main cause of current remote signalling action accuracy is the shake, electromagnetic interference, the loose contact of remote signalling loop, passage error code of switch auxiliary contact or relay etc.Because the link that causes malfunction and fail to report is numerous, the remote signalling enormous amount, search difficult.And the malfunction of circuit breaker and disconnecting link position and important guard signal and fail to report and cause serious interference by power grid accident is processed, and will produce other remote signalling action distrusts.Therefore must work harder, steadily improve remote signalling action accuracy.
The examination of remote signalling action accuracy refers to remote signalling correct operation number of times and correct operation number of times+tripping, the percentage of malfunction number of times sum, electric substation's measure and control device is N, here supposition has 50 measure and control devices and has respectively accessed sky, a road pulse idle contact signal, at the sky pulse action arranged constantly, these measure and control devices have all produced one and have taken turns action and return after pulse in SOE(days is arranged in action 1S and return), should send altogether 100 SOE signals, according to this electric substation's computer supervisory control system and upper level system thereof receive this action and return the SOE signal the number (containing tripping and malfunction), just can calculate respectively in said system the remote signalling action accuracy in the 1S time interval belonged in this electric substation's scope.
If this electric substation's computer supervisory control system remote signalling action accuracy is high, and its upper level system accuracy is low, illustrates that may there be the error code phenomenon in electric substation toward the teletransmission passage of upper level system, but emphasis solves the channel quality problem.If leak to send out a day pulse signal and cause remote signalling action accuracy to descend due to the minority measure and control device, it may be the remote signalling power work abnormal (short circuit or broken string) of these devices or measure and control device and the fault or unstable of having communicated by letter of station level system.In a word, the mistake existed according to each system is posted a letter or is failed to report the comparisons such as the number of number of times and abnormal device occurrence number, can very fast delineation abnormality scope, thus fix a breakdown targetedly.
The test of system remote signalling response time:
Because moment of sky pulse action is known fixed time, be equivalent to carve at this moment the on-the-spot remote signalling action event that occurs of measure and control device, we can start the stopwatch counting in this known moment, statistics electric substation computer supervisory control system, Masterstation Automation System or power network schedule automation main station system picture disply to or detect this and move the required response time and whether meet specifically applicable rules requirement.
The time accuracy test:
Because moment of sky pulse action is known fixed time, each measure and control device all will produce respectively a SOE displacement information after receiving day pulse action information, and stamp timestamp separately, this electric substation's computer supervisory control system and upper level system thereof also all can be stamped mark operate time according to the system time of oneself after receiving these remote signalling displacement information, therefore by check concrete SOE displacement information can judge corresponding measure and control device to the time precision, can verify this electric substation's computer supervisory control system and each own time accuracy of upper level system thereof according to the remote signalling displacement information corresponding with certain SOE displacement information.For instance, the moment of supposing first electric substation sky pulse action is set as 16: 0: 0 of every day, the sky pulse SOE displacement information of sending on regional power grid scheduling automation main website system is received first electric substation No. 1, No. 2 etc. measure and control device is all 000 millisecond of 16: 0: 0 on the 1st October (date information is omitted in following discussion) in 2011, illustrate first electric substation measure and control device accept clock synchronization system to the time normal; If it is 998 milliseconds of 16: 0: 0 001 millisecond or 15: 59: 59 that the sky pulse SOE displacement information of sending on the part measure and control device is arranged, explanation have the part measure and control device to the time have a fast or partially slow phenomenon; If the sky pulse SOE displacement information of sending on a lot of or whole measure and control devices be not 16: 0: 0 000 millisecond, need the operation such as electric substation's review time synchro system signal source, day pulse unit or whether normally arrange.If the scheduling station system is when receiving above-mentioned 16 o'clock 0 minute 0 second SOE of 000 millisecond, the remote signalling displacement time of its record is 16: 0: 5 or 15: 59: 54, and the test of main station system remote signalling response time meets the quantity of state displacement and is transferred to main station time≤3s, illustrating that main station system is punctual exists fast or partially slow phenomenon, corrective system time in time.
Remote signalling displacement test:
In current automation system for the power network dispatching at different levels still ubiquity remote signalling wrong report and fail to report phenomenon, being the shown remote signalling state of all kinds of remote ports of dispatch automated system (electric substation's computer supervisory control system, Masterstation Automation System, scheduling station system) does not conform to or leaks activating alarm information with the source signal state of electric substation reality, the dispatch automated system confidence level is descended, be unfavorable for that the administration of power networks personnel grasp the operation of power networks situation in real time, the correct judgement of impact to power grid accident and abnormal conditions.Therefore in dispatch automated system, remote signalling is a vital ring in " four is distant ", and especially remote signalling displacement power network schedule automation rules also require preferential transmission.The on-the-spot rules of the electric substation's telemechanical also main contents of regulation tour telecontrol equipment should comprise inspection remote signalling state, do in case of necessity positioning test.The link whether the remote signalling displacement normally involves is more, for instance, on-the-spot certain breaker operator displacement, the main website remote signalling is really reactionless, and main cause may have:
(1) lose during the main website process information;
(2) because of channel failure, lose;
(3) measure and control device or telemechanical master control plant failure, the remote signalling unreacted;
(4) loose contact of switch auxiliary contact or relay do not move.
This test macro can every day timing automatic the measure and control devices of electric substation's all accesses day pulse idle contact are produced to one-off and involution remote signalling displacements, be equivalent to every day the remote signaling function of measure and control device be done to once health check-up comprehensively, record remote signalling displacement information by verifying on-the-spot remote signalling displacement roll-call action character and a distant place, receive sequence of events recording SOE tripartite consistency, investigate the measure and control device unimpeded accuracy of communicating by letter with distant place automated system, find in time said apparatus and system and the configuration of main factory station data storehouse point table, the telecontrol channel tissue, communication protocol, the weak link of traffic rate, carry out targetedly malfunction elimination and rectification, improve work quality and efficiency.
The SOE instation test:
The SOE event is a kind of input of the switching value with synchronized timestamp displacement event, and the SOE module not only will gather the state of remote signalling displacement, the moment of also wanting the displacement of synchronous recording remote signalling state to occur.In substation automation system, sequence of events recording-SOE(Sequence of Events) critical function is exactly the sequencing that in the time of will correctly distinguishing electric network fault, all kinds of events occur, for correctly processing accident of dispatching of power netwoks operations staff, analysis and judgement electric network fault provide important means.Thereby, in electrical network SOE correctly record extremely important.
Access electric substation many measure and control device quantity of states are opened the sky pulse action displacement simultaneously constantly that the sky pulse idle contact into terminal is arranging, a plurality of remote signalling action event that are equivalent to simulated field, whether test electric substation's computer supervisory control system and upper level system thereof can correctly identify two and above remote signalling action event in same electric substation.
Test between the SOE station:
By first, synchronization all is arranged in the action of second electric substation sky pulse constantly, or the sky pulse action of first electric substation is arranged to integral point constantly constantly, pulse (1PPH when existing with second electric substation, pulse duration 1S) actuating signal compares, test the first and second two same upper level systems that electric substation belongs to and whether can correctly identify two and above action event in different electric substations, and the precedence of the different SOE of the electric substation information arrival that receive, the communication protocol of the first and second two electric substations and upper level automated system relatively accordingly, traffic rate, communication mode and processing response time quality.
The test of remote signalling storm:
According to standby of concrete measure and control device remote signalling unit, scene quantity, every measure and control device accesses a road or sky, some roads pulse signal intake, the total remote signalling amount of day pulse is expanded to meet the quantity of remote signalling storm test, thereby test tested electric substation computer supervisory control system and upper level system thereof the disposal ability to a large amount of remote signalling displacement in scene event.
General electric substation measure and control device is all two specifically, more than 30, some 500kV electric substation even can reach nearly 60, if 55 measure and control devices of first electric substation are access 1 sky, road pulse idle contact signal all, first electric substation returns constantly and all will export a large amount of remote signalling displacements in the 1S interval altogether with action at the sky pulse action, add up 110 remote signalling displacements, if gps clock signal extension device sky pulse unit quantity is enough, give all access 2 sky, road pulse idle contact signals of every measure and control device, the remote signalling displacement will expand to 220, can test tested electric substation computer supervisory control system and upper level system thereof the disposal ability to a large amount of remote signalling displacement in scene event fully.
In sum, native system and method for testing thereof have following characteristics:
Low-cost: this test macro is based on the dispatching automation of electric power systems present situation, current each Comprehensive Automation Substation all is equipped with a set of satellite clock signal receiving device that enough fan-out capabilities are arranged, usually by one or more surfaces clock apparatus screen, formed, the master clock device receiving element receives Coordinated Universal Time(UTC) (UTC) signal of satellite transmission as the external time reference signal, provides time reference signal to the clock signal expanding unit simultaneously.Configurable one or more signal extension case as required in each clock of clock synchronization system screen, the signal extension case provides multiplex pulse signal (1PPS, 1PPM, 1PPH, 1PPD idle contact, difference, TTL etc.), IRIG-B signal, DCF77 signal, time message, NTP network time signal, can meet distinct device in electric substation to the time interface requirement, the quantity of signal extension case and output signal interface type according in each function cell to the time equipment concrete condition determine.
This test macro is received the stand-by state amount input terminal of every measure and control device in station to some road 1PPD idle contacts (pulse duration 1S) signal of a plurality of days pulse units (1PPD) of Substation Time Synchronous System output by the general control cable, this control cables can discharge separately or utilize the standby core access of existing same paths cable.In addition, native system does not need other inputs, and construction cost is low.
Normalization: this test macro regularly produces one-off and involution remote signalling displacement to the measure and control device of electric substation's all accesses day pulse idle contact in the moment of setting every day automatically, be equivalent to every day the remote signaling function of measure and control device be done to once health check-up comprehensively, the dispatching automation operator on duty can be at the sky pulse action constantly or verify call the roll action character and a distant place of on-the-spot remote signalling displacement by historical record and record remote signalling displacement information, receive sequence of events recording SOE tripartite's content and quantitative consistency, can find as early as possible in time measure and control device to the time not to upper, remote signalling power supply dead electricity, remote signalling is reported by mistake and is failed to report, remote control communication equipment is uploaded Masterstation Automation System or scheduling station system database and is partly put the fault that table configuration sequence entanglement etc. is difficult for discovering.
Automation: the every genius frequency of this test macro produces once concentrated action and involution remote signalling displacement to the measure and control device of electric substation's all accesses day pulse idle contact automatically, if the electric substation implemented by this system pattern is more, these electric substations can be arranged to different sky pulse actions constantly, therefore can not give each link of dispatch automated system brings excessive interference and increases added burden, test process starts automation, do not need manual intervention, the dispatching automation personnel can be according to concrete test event, carrying out relevant prepare or by relevant system historical record constantly at the sky pulse action, to measure and control device, electric substation's computer supervisory control system and upper level system thereof (Masterstation Automation System or power network schedule automation main station system) are carried out index of correlation, functional test and statistics.
Standardization: this test macro regularly produces one-off and involution remote signalling displacement to all day measure and control devices of pulse idle contact that access of electric substation every day again and again automatically, action time started and the involution of displacement are certain interval time, quantity necessarily and is in advance predicted, so science Telemetry device with a definite target in view, electric substation's computer supervisory control system and upper level system thereof (Masterstation Automation System or power network schedule automation main station system) are processed the ability of remote signalling displacement and SOE, the Specifications of remote signaling function in examination said apparatus and system, whether function meets the requirement of normal operation, and carry out targetedly the rectification of fault and weak link, guarantee accurately, reflect in real time action message, guarantee the dispatch automated system reliability service.
Apply situation:
The above is exemplarily described the present invention by reference to the accompanying drawings; obviously specific implementation of the present invention is not subject to the restrictions described above; as long as adopted the improvement of the various unsubstantialities that method of the present invention design and technical scheme carry out; or without improving, design of the present invention and technical scheme are directly applied to other occasion, all within protection scope of the present invention.

Claims (2)

1. one kind is utilized electric substation's measure and control device remote signalling to measure the method for testing of test system to the remote signalling response time, it is characterized in that: this system be provided with to all automation equipments output in an electric substation to the time signal the satellite time transfer device, described satellite time transfer device is provided with the multicircuit time pulse unit, and the idle contact of output day pulse simultaneously signal is to the measure and control device in described automation equipment, described measure and control device remote signalling unit is sent to electric substation's computer supervisory control system by the SOE displacement information of its generation after receiving this pulse, and the output of the upper level automated system outside electric substation by remote control communication equipment,
Send pulse at the satellite time transfer device and constantly start the stopwatch counting, to adding up electric substation's computer supervisory control system and upper level system, detect or show that the moment of SOE signal is the remote signalling response time.
2. the method for testing of remote signalling response time according to claim 1 is characterized in that: described idle contact signal is the pulse signal that the pulse duration regularly sent every day is 1S.
CN201310156096.6A 2011-10-28 2011-10-28 A kind of electric substation's measure and control device remote signalling measurement test system that utilizes is to the method for testing of remote signalling response time Active CN103490506B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310156096.6A CN103490506B (en) 2011-10-28 2011-10-28 A kind of electric substation's measure and control device remote signalling measurement test system that utilizes is to the method for testing of remote signalling response time

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201110333590.6A CN102361356B (en) 2011-10-28 2011-10-28 System and method for testing remote communication volume of transformer substation testing-controlling device
CN201310156096.6A CN103490506B (en) 2011-10-28 2011-10-28 A kind of electric substation's measure and control device remote signalling measurement test system that utilizes is to the method for testing of remote signalling response time

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201110333590.6A Division CN102361356B (en) 2011-10-28 2011-10-28 System and method for testing remote communication volume of transformer substation testing-controlling device

Publications (2)

Publication Number Publication Date
CN103490506A true CN103490506A (en) 2014-01-01
CN103490506B CN103490506B (en) 2016-03-02

Family

ID=45586621

Family Applications (6)

Application Number Title Priority Date Filing Date
CN201310156076.9A Active CN103490505B (en) 2011-10-28 2011-10-28 A kind of electric substation's measure and control device remote signalling measurement test system that utilizes is to the method for SOE test in station
CN201310156028.XA Active CN103490504B (en) 2011-10-28 2011-10-28 Method for testing inter-station SOE through substation measuring and control device telecommand quantity testing system
CN201310156096.6A Active CN103490506B (en) 2011-10-28 2011-10-28 A kind of electric substation's measure and control device remote signalling measurement test system that utilizes is to the method for testing of remote signalling response time
CN201310156906.8A Active CN103368259B (en) 2011-10-28 2011-10-28 A kind of electric substation's measure and control device remote signalling measurement test system that utilizes is to the method for testing of time accuracy
CN201310154232.8A Active CN103368257B (en) 2011-10-28 2011-10-28 A kind of method utilizing electric substation's measure and control device remote signalling measurement test system to test remote signalling storm
CN201110333590.6A Active CN102361356B (en) 2011-10-28 2011-10-28 System and method for testing remote communication volume of transformer substation testing-controlling device

Family Applications Before (2)

Application Number Title Priority Date Filing Date
CN201310156076.9A Active CN103490505B (en) 2011-10-28 2011-10-28 A kind of electric substation's measure and control device remote signalling measurement test system that utilizes is to the method for SOE test in station
CN201310156028.XA Active CN103490504B (en) 2011-10-28 2011-10-28 Method for testing inter-station SOE through substation measuring and control device telecommand quantity testing system

Family Applications After (3)

Application Number Title Priority Date Filing Date
CN201310156906.8A Active CN103368259B (en) 2011-10-28 2011-10-28 A kind of electric substation's measure and control device remote signalling measurement test system that utilizes is to the method for testing of time accuracy
CN201310154232.8A Active CN103368257B (en) 2011-10-28 2011-10-28 A kind of method utilizing electric substation's measure and control device remote signalling measurement test system to test remote signalling storm
CN201110333590.6A Active CN102361356B (en) 2011-10-28 2011-10-28 System and method for testing remote communication volume of transformer substation testing-controlling device

Country Status (1)

Country Link
CN (6) CN103490505B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104269938A (en) * 2014-10-25 2015-01-07 国家电网公司 Device and method for detecting faults of station dispatching automation equipment
CN109143072A (en) * 2017-06-28 2019-01-04 东软集团股份有限公司 A kind of test method of battery management system, device and equipment
CN111668938A (en) * 2020-06-17 2020-09-15 南京太司德智能电气有限公司 Method for realizing simulation remote control of electric power measurement and control device
CN113169903A (en) * 2018-12-07 2021-07-23 罗伯特·博世有限公司 Simultaneous testing of multiple electronic devices connected via a communication network for correct handling of exceptions

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102761320B (en) * 2012-07-13 2014-10-08 北京控制工程研究所 Digital quantity telemetering circuit
CN103412558B (en) * 2013-07-30 2016-01-13 国电南瑞科技股份有限公司 Measurement and Control Equipment for Relay Protection Auto-Test System and method
CN103699103B (en) * 2013-12-30 2016-08-17 上海自动化仪表有限公司 The method of sequence of events recording in scattered control system
CN104022914A (en) * 2014-04-26 2014-09-03 广西电网公司电力科学研究院 Method for automatic terminal function detection of distribution network
CN104155557B (en) * 2014-09-04 2017-02-01 国家电网公司 Special testing device for remote signaling and remote control of transformer substation
CN106027178B (en) * 2016-06-15 2018-05-04 国网福建省电力有限公司 A kind of electric power scheduling automatization system telemeter time test method based on step response
CN106053960A (en) * 2016-07-07 2016-10-26 南京大贺电力科技有限公司 Power automatic network analysis apparatus
CN106569404B (en) * 2016-11-01 2019-04-12 国电南瑞科技股份有限公司 A kind of secondary device clock step-out on-line monitoring system and method
CN107205056B (en) * 2017-08-02 2020-02-18 广东电网有限责任公司电力调度控制中心 Method and system for scheduling master station by delayed response of telecontrol device
CN110134632B (en) * 2019-05-10 2021-06-18 北京和利时系统工程有限公司 Timing processing method and device and computer storage medium
CN110187258B (en) * 2019-05-13 2024-04-02 国网宁夏电力有限公司培训中心 Remote control loop tester of measurement and control device
CN110837005B (en) * 2019-11-13 2022-06-21 国家电网有限公司 Method for detecting output pulse width precision of automation and protection equipment
CN110994792B (en) * 2019-12-05 2023-08-04 广东电网有限责任公司 System for detecting signal during power grid equipment power restoration
CN111211849B (en) * 2020-01-10 2022-06-17 武汉船舶通信研究所(中国船舶重工集团公司第七二二研究所) Method and apparatus for high frequency communication channel sounding
CN111639876B (en) * 2020-06-07 2022-05-17 电管家能源管理(上海)有限公司 Main station connection and calculation system
CN111769642A (en) * 2020-07-03 2020-10-13 积成软件有限公司 Processing method for preventing mistaken development of incoming telecommand deflection information during power failure
CN111983444B (en) * 2020-08-28 2021-06-08 国网山东省电力公司郯城县供电公司 Circuit breaker misoperation detection system of comprehensive automatic power distribution system
CN112556749A (en) * 2020-11-30 2021-03-26 薛峰 Detection method for redundant measurement and control device
CN112556750B (en) * 2020-11-30 2022-06-21 薛峰 Function detection method of cluster measurement and control device
CN113972736A (en) * 2021-10-13 2022-01-25 国网福建省电力有限公司电力科学研究院 Method and device for interaction of running state information of power secondary equipment

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5179376A (en) * 1991-02-28 1993-01-12 Systems Analysis And Integration, Inc. Substation load distribution monitor system
CN1801023A (en) * 2005-11-14 2006-07-12 杨卫民 Multi-event sequential recording and testing system
CN102437654A (en) * 2011-12-31 2012-05-02 国电南京自动化股份有限公司 Station control realizing method based on monitoring system

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10191473A (en) * 1996-12-25 1998-07-21 Mitsubishi Electric Corp Monitor control system
CN101192900B (en) * 2006-12-01 2011-05-11 武汉烽火网络有限责任公司 Communication method and device for application forward error correction mechanism of carrier-class Ethernet
JP2009065778A (en) * 2007-09-06 2009-03-26 Tokyo Electric Power Co Inc:The Power system monitor control system
CN201348514Y (en) * 2008-12-15 2009-11-18 北京国电智深控制技术有限公司 Testing signal generator for sequence of event
WO2011030190A1 (en) * 2009-09-14 2011-03-17 Abb Technology Ltd A method and a system for simulation in a substation
CN201828585U (en) * 2010-10-20 2011-05-11 国电南瑞科技股份有限公司 Portable transformer substation synchronous time ticking and SOE signal generator
CN202340147U (en) * 2011-10-28 2012-07-18 安徽省电力公司芜湖供电公司 Remote signaling quantity testing system of measuring and control device of power substation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5179376A (en) * 1991-02-28 1993-01-12 Systems Analysis And Integration, Inc. Substation load distribution monitor system
CN1801023A (en) * 2005-11-14 2006-07-12 杨卫民 Multi-event sequential recording and testing system
CN102437654A (en) * 2011-12-31 2012-05-02 国电南京自动化股份有限公司 Station control realizing method based on monitoring system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104269938A (en) * 2014-10-25 2015-01-07 国家电网公司 Device and method for detecting faults of station dispatching automation equipment
CN109143072A (en) * 2017-06-28 2019-01-04 东软集团股份有限公司 A kind of test method of battery management system, device and equipment
CN113169903A (en) * 2018-12-07 2021-07-23 罗伯特·博世有限公司 Simultaneous testing of multiple electronic devices connected via a communication network for correct handling of exceptions
CN111668938A (en) * 2020-06-17 2020-09-15 南京太司德智能电气有限公司 Method for realizing simulation remote control of electric power measurement and control device
CN111668938B (en) * 2020-06-17 2023-08-04 南京太司德智能电气有限公司 Method for realizing analog remote control of electric power measurement and control device

Also Published As

Publication number Publication date
CN103368259B (en) 2015-11-04
CN103490505A (en) 2014-01-01
CN103490504A (en) 2014-01-01
CN103368257A (en) 2013-10-23
CN102361356A (en) 2012-02-22
CN103490504B (en) 2015-07-15
CN103490505B (en) 2016-02-24
CN102361356B (en) 2014-05-28
CN103368259A (en) 2013-10-23
CN103368257B (en) 2015-08-05
CN103490506B (en) 2016-03-02

Similar Documents

Publication Publication Date Title
CN102361356B (en) System and method for testing remote communication volume of transformer substation testing-controlling device
CN102055544B (en) System and method for synchronously monitoring secondary equipment time of power supply system
CN201867455U (en) Electronic mutual indicator test system
CN109900994B (en) Intelligent substation secondary circuit comprehensive performance test system and working method
CN110048507B (en) Automatic inspection method and system for power distribution automation system
CN104935079A (en) Station-domain protection system of intelligent transformer station and function debugging method of system
CN201425705Y (en) Electric power system time synchronizer
CN103412477A (en) Timing system capable of guaranteeing full-grid time synchronization of power grid
CN201425704Y (en) Satellite synchronous main clock device
CN103293414A (en) Intelligent substation protection device synchronization performance test system and method based on GPS (globe positioning system) accurate time synchronization technology
CN203465541U (en) Beidou/GPS double-time service source-based failure time recording device
CN202340147U (en) Remote signaling quantity testing system of measuring and control device of power substation
Knezev et al. Automated circuit breaker monitoring
CN102591195A (en) Mutual inspection method for mutually backup double clock, and time comparing device
CN104734338A (en) Clock monitoring method, device and system of transformer substations
CN102200559B (en) Regional remote spare power source automatic transfer test method and related equipment
CN202353575U (en) Time synchronization real-time monitoring device
CN103576014A (en) Clock monitoring device and monitoring method of transformer substation
CN103368258B (en) Method for testing telecommand deflection by telecommand quantity testing system of measuring and control device of substation
CN202615137U (en) Time service unifying device of electrical power system
CN202940820U (en) Clock synchronization network system based on transparent clock
CN214041605U (en) Edge computing system and power distribution terminal with high-low voltage synchronous measurement and protection
CN112180212A (en) Edge computing system, method and terminal with high-low voltage synchronous measurement and protection
JP2002233081A (en) Equipment monitoring control system
CN202008512U (en) Dynamic analog tester for regional remote standby power automatic switch-in equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: STATE GRID WUHU POWER SUPPLY CO., LTD. OF ANHUI ELECTRIC POWER CO., LTD.

Effective date: 20140505

Owner name: STATE GRID WUHU POWER SUPPLY CO., LTD. OF ANHUI EL

Effective date: 20140505

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 241000 No. 18, Zhongshan North Road, Anhui, Wuhu

Applicant after: STATE GRID ANHUI WUHU POWER SUPPLY Co.

Address before: 241000 Zhongshan North Road, Jinghu, Anhui, No. 18,

Applicant before: ANHUI WUHU POWER SUPPLY Co.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: ANHUI ELECTRIC POWER CORPORATION, WUHU POWER SUPPLY COMPANY TO: STATE GRID WUHU POWER SUPPLY CO., LTD. OF ANHUI ELECTRIC POWER CO., LTD.

Free format text: CORRECT: ADDRESS; FROM: 241000 WUHU, ANHUI PROVINCE TO: 100031 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20140505

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: STATE GRID ANHUI WUHU POWER SUPPLY Co.

Address before: 241000 No. 18, Zhongshan North Road, Anhui, Wuhu

Applicant before: STATE GRID ANHUI WUHU POWER SUPPLY Co.

C14 Grant of patent or utility model
GR01 Patent grant