CA2509867A1 - Hierarchical projects in a computer-enabled project management method and system - Google Patents

Hierarchical projects in a computer-enabled project management method and system Download PDF

Info

Publication number
CA2509867A1
CA2509867A1 CA002509867A CA2509867A CA2509867A1 CA 2509867 A1 CA2509867 A1 CA 2509867A1 CA 002509867 A CA002509867 A CA 002509867A CA 2509867 A CA2509867 A CA 2509867A CA 2509867 A1 CA2509867 A1 CA 2509867A1
Authority
CA
Canada
Prior art keywords
project
schedule
sub
project schedule
change
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
CA002509867A
Other languages
French (fr)
Inventor
Roy Kayahara
Raju Iyer
Nichol C. Viton
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Microsoft Technology Licensing LLC
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of CA2509867A1 publication Critical patent/CA2509867A1/en
Abandoned legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • G06Q50/50

Abstract

Methods and systems are provided for establishing a hierarchical relationship between a parent or master project schedule and sub-project schedules including tasks and phases required for completion of the parent or master project. When changes are made to data contained in a given parent or master project schedule or to a hierarchically related sub-project schedule, an automatic notification is passed to the owners/managers of affected project schedules so that those parties may accept the proposed change, reject the proposed change, or respond to the submitting party with a counter change proposal.

Description

HIERARCHICAL PROJECTS IN A COMPUTER-ENABLED
PROJECT MANAGEMENT METHOD AND SYSTEM
Field of the Invention The present invention generally relates to project management methods and systems. More particularly, the present invention relates to hierarchically related projects in a project management method and system.
Background of the Invention With the advent of the computer age, computer and software users have grown accustomed to user-friendly software applications that help them write, calculate, organize, prepare presentations, send and receive electronic mail, make music, and the like. Modern word processing applications, for example, allow users to create and edit a variety of useful documents. Modern project management applications, for another example, allow users to create project schedules for organizing and managing tasks, resources and the labor associated with a variety of projects.
Manual and computerized project management systems allow managers and planners to organize and schedule the tasks, resources and timing required for completion of a given project. In most projects, a number of dependencies and constraints dictate the timing and completion of an overall project and of sub-projects contained in the overall project. For example, in a house construction project, a drywall project may not typically begin until the completion of electrical work. And, a number of sub-projects may be constrained by the availability of labor and resources.
Project management software applications have been developed for creating and automating project schedules. With many such systems, tasks or sub-projects within an overall project are set out showing start dates, completion dates and information regarding utilized resources or constraints thereon.
Prior project management schedules typically may be edited by any person having edit permissions, and changes made to a given schedule are automatically made throughout the schedule without warning to other affected parties. For example, following the example construction project set out above, if an electrician makes changes to his/her portion of a house construction project schedule, a drywall professional's schedule may be automatically changed without notice to the drywall professional. Some systems have been developed to allow the owner/manager of a sub-project within an overall project to independently manage the sub-project schedule, but because the performance of the sub-project may serve as a constraint on the performance of the overall project, changes to the sub-project schedule nonetheless cause changes to the overall project and to other sub-projects comprising the overall project. Because of these types of problems, the project schedule is often reduced to a mere snapshot view of the project schedule which must be closely monitored by all project participants due to the nature of such automated changes and to the lack of automated notification of changes to the project participants.
Accordingly, there is a need for improved project management methods and systems that allow for independent management of sub-projects, and that allow for notification and change acceptance to and from project participants. It is with respect to these and other considerations that the present invention has been made.
Summary of the Invention Embodiments of the present invention solve the above and other problems by providing an improved automated project management method and system wherein sub-projects of an overall project are related hierarchically to the overall project and to other sub-projects (if required), and wherein changes made to one or more sub-projects or to the overall project are persisted in the overall project and to the affected sub-projects through notification and acceptance/rejection/counter change to and from the affected project/sub-project owners/managers.
According to an aspect of the invention, a hierarchical relationship is established between a set of projects comprising an overall project wherein the overall project has a parent/child relationship to sub-projects comprising the overall project, and whereby a given sub-project may have a parent/child relationship with sub-projects comprising the
2 given sub-project. Target dates for completion of sub-projects and included tasks are passed from the parent project down to child sub-projects comprising the parent project.
Independently manageable child sub-project schedules are constructed and are passed back to the parent project for construction of a parent project schedule.
If a change in the parent schedule is made that affects one or more child sub-projects, a notification is sent to the owner/manager of each affected child sub-project.
Upon receipt of the change from the parent project, an affected child sub-project may accept the change, and the child sub-project is automatically updated to reflect the accepted change. Alternatively, if the owner/manager of an affected child sub-project finds the change from the parent project unacceptable, a counter change may be proposed from the child sub-project back to the parent project. Upon notification of the counter change from the child sub-project, the parent project owner/manager may accept or reject the counter change.
If the parent project rejects the counter change, the submitting child sub-project is notified, and the original change passed to the child sub-project schedule from the parent project schedule is automatically accepted by the child sub-project schedule, and any changes to the child sub-project schedule required by the change are made.
If the parent project schedule accepts the counter change, a notification of the counter change is passed to all affected child sub-projects by the parent project schedule for acceptance by receiving child sub-projects wherefore further counter change from receiving child sub-projects.
If a given child sub-project owner/manager submits a proposed change to the parent project schedule, the parent project owner/manager may accept or reject the proposed change. If the parent project accepts the proposed change, then a notification is sent to all affected child sub-project owners/managers who may accept or propose counter changes.
According to another aspect of the invention, each child sub-project schedule may be managed and changed independently from the parent project schedule or other child sub-project schedules, but changes made to individual child sub-project schedules are only made to the parent project schedule and to other child sub-project schedules
3 through the notification/acceptance/rejection/counter change process described above.
Given proper access permissions, the owner/manager of the parent project schedule or owners/managers of other child sub-project schedules may access and view other child sub-project schedules to review changes or variances made to project schedules.
These and other features and advantages, which characterize the present invention, will be apparent from a reading of the following detailed description and a review of the associated drawings. It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the invention as claimed.
Brief Description of the Drawings Fig. 1 illustrates an exemplary computing operating environment for embodiments of the present invention.
Fig. 2 is a simplified block diagram of a distributed computing environment through which the owners/managers of a parent project and one or more child sub projects may communicate to a project server/database for creation and maintenance of a project schedule according to embodiments of the present invention.
Fig. 3 are simplified block diagrams illustrating hierarchical relationships between parent and child sub-projects in an overall project schedule according to embodiments of the present invention.
Fig. 4 is a flow diagram showing an illustrative routine for creating and managing parent and hierarchically related child sub-projects according to embodiments of the present invention.
Detailed Descriution of the Preferred Embodiment As briefly described above, embodiments of the present invention are directed to improved automated project management methods and systems wherein sub-projects of an overall project are related hierarchically to the overall project and wherein changes made to one or more sub-projects or to the overall project are persisted in the overall project and to the sub-projects through a notification and acceptance/rejection/counter
4 change process between a parent project of the overall project and affected child sub-projects of the parent project. When a change made in a child sub-project is submitted for acceptance by the parent project, a notification is sent to the owner/manager of the parent project who may accept or reject the proposed change. If the proposed change is accepted, the parent project owner/manager submits the change to all affected child sub-projects along with a notification to the owners/managers of the child sub-projects. The owners/managers of the child sub-projects may accept the change or may propose a counter change back to the parent project. Individual child sub-projects may be managed independently from the overall project, but changes made to individual child sub-project schedules axe made to the overall project only after the notification and acceptance/rejection/counter change process described herein.
By separating the overall project into independently manageable sub-project schedules, the owners/managers of the sub-project schedules comprising an overall parent or master project schedule may manage their own respective schedules without automatically making changes without warning to the overall project schedule each time an owner/manager affects changes in his or her respective sub-project schedule.
For example, if the owner/manager of a given sub-project schedule realizes that a given task or sub-task may require an extra week to complete, the owner/manager of the sub-project schedule may make changes to his/her sub-project schedule without submitting those changes to any affected upstream parent project schedule or affected downstream sub-project schedule if the owner/manager of the changed sub-project schedule knows that the sub-project will be completed on the original schedule notwithstanding the change made to some discrete portion of the sub-project schedule. For example, the owner/manager of the sub-project may know that additional labor or resources will be utilized to ultimately cause the sub-project to be completed on the original schedule notwithstanding the change made to a given task or phase contained in the sub-project schedule. Thus, the owner/manager of the affected sub-project schedule may independently manage his/her sub-project without automatically making changes to a published overall project schedule.
5 On the other hand, if the owner/manager of the affected sub-project schedule realizes that the change in his/her schedule may not be overcome, the change may be submitted upstream to a parent project schedule owner/manager or to downstream sub-project schedule owners/managers for acceptance, rejection, or counter change, as described herein. Thus, embodiments of the present invention allow for owners/managers of individual project schedules to independently manage their own respective project schedules apart from other project schedules or sub-project schedules to which their project schedule is related. Only when the owner/manager of a given project schedule desires to submit a scheduled change upstream to a parent project schedule or downstream to one or more sub-project schedules does the automatic notification method and system described herein operate.
In the following detailed description, references are made to the accompanying drawings that form a part hereof, and in which are shown by way of illustrations specific embodiments or examples. These embodiments may be combined, other embodiments may be utilized, and structural changes may be made without departing from the spirit or scope of the present invention. The following detailed description is therefore not to be taken in a limiting sense and the scope of the present invention is defined by the appended claims and their equivalents.
Referring now to the drawings, in which like numerals represent like elements through the several figures, aspects of the present invention and the exemplary operating environment will be described. Fig. 1 and the following discussion are intended to provide a brief, general description of a suitable computing environment in which the invention may be implemented. While the invention will be described in the general context of program modules that execute in conjunction with an application program that runs on an operating system on a personal computer, those skilled in the art will recognize that the invention may also be implemented in combination with other program modules.
Generally, program modules include routines, programs, components, data structures, and other types of structures that perform particular tasks or implement particular abstract data types. Moreover, those skilled in the art will appreciate that the
6 invention may be practiced with other computer system configurations, including hand-held devices, multiprocessor systems, microprocessor-based or programmable consumer electronics, minicomputers, mainframe computers, and the like. The invention may also be practiced in distributed computing environments where tasks are performed by remote processing devices that are linked through a communications network. In a distributed computing environment, program modules may be located in both local and remote memory storage devices.
Turning now to Fig. 1, an illustrative computer architecture for a personal computer 2 for practicing the various embodiments of the invention will be described.
The computer architecture shown in Fig. 1 illustrates a conventional personal computer, including a central processing unit 4 ("CPU"), a system memory 6, including a random access memory 8 ("RAM") and a read-only memory ("ROM") 10, and a system bus 12 that couples the memory to the CPU 4. A basic input/output system containing the basic routines that help to transfer information between elements within the computer, such as during startup, is stored in the ROM 10. The personal computer 2 further includes a mass storage device 14 for storing an operating system 16, application programs, such as the application program 205, and data.
The mass storage device 14 is connected to the CPU 4 through a mass storage controller (not shown) connected to the bus 12. The mass storage device 14 and its associated computer-readable media, provide non-volatile storage for the personal computer 2. Although the description of computer-readable media contained herein refers to a mass storage device, such as a hard disk or CD-ROM drive, it should be appreciated by those skilled in the art that computer-readable media can be any available media that can be accessed by the personal computer 2.
By way of example, and not limitation, computer-readable media may comprise computer storage media and communication media. Computer storage media includes volatile and non-volatile, removable and non-removable media implemented in any method or technology for storage of information such as computer-readable instructions, data structures, program modules or other data. Computer storage media includes, but is not limited to, RAM, ROM, EPROM, EEPROM, flash memory or other
7 solid state memory technology, CD-ROM, DVD, or other optical storage, magnetic cassettes, magnetic tape, magnetic disk storage or other magnetic storage devices, or any other medium which can be used to store the desired information and which can be accessed by the computer.
According to various embodiments of the invention, the personal computer 2 may operate in a networked environment using logical connections to remote computers through a TCP/IP network 18, such as the Internet. The personal computer 2 may connect to the TCP/IP network 18 through a network interface unit 20 connected to the bus 12. It should be appreciated that the network interface unit 20 may also be utilized to connect to other types of networks and remote computer systems. The personal computer 2 may also include an input/output controller 22 for receiving and processing input from a number of devices, including a keyboard or mouse (not shown).
Similarly, an input/output controller 22 may provide output to a display screen, a printer, or other type of output device.
As mentioned briefly above, a number of program modules and data files may be stored in the mass storage device 14 and RAM 8 of the personal computer 2, including an operating system 16 suitable for controlling the operation of a networked personal computer, such as the WINDOWS operating systems from Microsoft Corporation of Redmond, Washington. The mass storage device 14 and RAM 8 may also store one or more application programs. In particular, the mass storage device 14 and RAM 8 may store an application program 105 for providing a variety of functionalities to a user. For instance, the application program 105 may comprise many types of programs such as a word processing application program, a spreadsheet application, an electronic mail application 130, a database application and the like.
According to embodiments of the present invention, a project management application 135 is included for preparing project schedules as described herein. An example project management application for use in accordance with the present invention is PROJECT
manufactured by Microsoft Corporation.
Fig. 2 is a simplified block diagram of a distributed computing environment through which the owners/managers of a parent project and one or more child sub-
8 projects may communicate to a project server/database for creation and maintenance of a project schedule according to embodiments of the present invention. The distributed computing environment 200 illustrated in Fig. 2 serves as an exemplary operating environment for embodiments of the present invention. As described herein, an overall project schedule may be comprised of a parent project schedule and one or more hierarchically related child sub-projects.
According to embodiments of the present invention, the overall or parent project schedule and individual and independently manageable child sub-project schedules are maintained on a project server/database 210. The project server/database 210 is a general purpose computing system having components including an operating system, a processor and memory space as described above for the computer 2 illustrated and described with reference to Fig. 1. The project server/database 210 also includes a project management application 135 having sufficient computer executable instructions for constructing, displaying and allowing management of the overall/parent project schedule and of the individual child sub-project schedules described herein.
The project server/database 210 also includes a relational database for maintaining data associated with the parent project schedule and for each of the individual child sub-project schedules. As should be understood by those skilled in the art, the relational database allows for information stored associated with one project schedule to be related to one or more other project schedules for exchanging stored data between disparate project schedules comprising the overall or parent project schedule described herein.
As illustrated in Fig. 2, the parent/master computer system 220 is illustrated for communication with the project server/database 2I0 via a distributed computing system such as the Internet or intranet 250. One or more child/sub-project computing systems 230, 240 are illustrated for communicating with the project server/database 210 via the Internet or intranet 250. As should be appreciated, the computing systems 220, 230, 240 operated by the owners/managers of the parent project schedule and of one or more child sub-project schedules comprising the parent project schedule may include the processing and memory functionality described above with reference to the computer 2,
9 illustrated in Fig. 1. Each of the individual computing systems 220, 230, 240 may also include a project management application 135 described above with reference to Fig. l, and serving as client-side project management applications to a corresponding project management application 135 operated at the project server/database 2I0.
According to embodiments of the present invention, the project server/database 210 may also include or may be operative to access an electronic mail application 130 for sending automatic project schedule changes to and from owners/managers of the parent project schedule and the child sub-project schedules.
According to embodiments of the present invention, the owner/manager of the parent project schedule may create the project schedule from the computing system 220 via the Internet or intranet 250 to the project server/database 210. Creation and maintenance of individual child sub-project schedules may likewise be created by owners/managers of the child sub-project schedules from the computing systems 230, 240 via the Internet/intranet 250 to the project server/database 210.
Notifications between the owners/managers of the parent project schedule and the one or more child sub-project schedules may be affected automatically by a communications application such as the electronic mail application 130 upon command by the project management application 135. That is, when a change or proposed change requires notification to the owner/manager of an affected project schedule or related sub-project schedule, the project management application 135 at the project server/database 210 may call a communications application such as the electronic mail application 130 and cause an appropriate notification message to be sent to the affected party. As should be understood by those skilled in the art, other forms of communication may be utilized for notification of affected parties including instant messaging systems, telephonic systems, and the like.
As is appreciated by those skilled in the art of project management methods and systems, a given project may include a number of tasks that must be completed and each task may be constrained by available resources and a required duration of time for completion of the task. Moreover, some tasks may not be initiated until the completion of a related task. For many projects, individual tasks comprising a given project are managed and processed under a separate and related project schedule. For example, a master project schedule may be prepared for constructing a house. The master project schedule may include three phases or tasks such as general framing, electrical and plumbing. Each of the phases or tasks of the master project may be completed by a subcontractor who constructs and manages his/her own project schedule for a given phase or task. For example, a first sub-project schedule may be constructed for general framing, a second sub-project schedule may be constructed for electrical work, and a third project schedule may be constructed for plumbing work. As should be appreciated, each of the sub-project schedules may be broken into one or more phases or tasks which may, in turn, be associated with additional sub-projects for completion of one or more tasks within a given sub-project.
According to embodiments of the present invention, a hierarchical relationship is established between related projects and associated sub-projects in a parent/child hierarchical relationship so that changes or proposed changes in any related schedule may be accepted, rejected, or otherwise responded to through a notification process as described herein. Referring now to Fig. 3, hierarchically related project schedules related to each other in association with an overall project and stored at the project management server/database 210 are illustrated. The overall project schedule 310 is illustrated as having three project phases that must be completed in order to complete the overall project. For example, the project schedule 310 may be a project schedule for constructing a house, described above. Phase 1 may include general framing, Phase 2 may include electric work, and Phase 3 may include plumbing work.
Once the owner/manager of the project schedule 310 establishes target dates for beginning and completing each of the phases of the project schedule 310, those target dates are passed down to owners/managers of required sub-projects for completing each phase of the master project schedule 310. For each of the sub-projects, a sub-project schedule may be constructed for managing and scheduling tasks required for completing the given sub-project. For example, the project schedule 310 may be illustrative of a sub-project schedule required for completing Phase 2 of the overall project schedule 310. Similarly, the project schedule 340 may include scheduling information required for completion of Task 2 of the project schedule 320. As illustrated in Fig. 3, the three project schedules are hierarchically related such that the master project schedule 310 serves as a parent schedule, the sub-project schedule 320 serves as a child schedule to the parent schedule 310, and the sub-project schedule 340 serves as a child sub-project schedule to the sub-project schedule 320.
In each of the illustrated project schedules 310, 320, 340, summary tasks are illustrated for grouping together one or more sub-tasks required for completion of a given task. For example, the Phase 2 summary task 315 illustrated in the parent project schedule 310 includes summary information related to all tasks, resources, constraints, and timing associated with completing Phase 2 of the parent project. The sub-project schedule 320 shows the summary task 316 that is linked to the summary task (Phase 2) 315 in the parent schedule 310. As should be appreciated, the summary task 316 illustrated in 320 contains summary information related to any tasks that must be completed for the completion of the Phase 2 summary task 316. Likewise, a Task summary task 331 is illustrated in the sub-project schedule 340 that is linked to the Task 2 schedule set out in the sub-project schedule 320.
As is well known to those skilled in the art, in a given project schedule, as illustrated in Fig. 3, certain tasks or phases of a project may not be initiated until the completion of another phase or task. For example, Phase 2 illustrated in the master/parent project schedule 310 may not be initiated until completion of Phase 1.
Similarly, Task 3 of the sub-project schedule 320 may not be initiated until completion of Task 1 of the project schedule 320. Consequently, if Phase 1 of the parent/master project schedule 310 is extended, the initiation of Phase 2 may be pushed out to a later start date. Changing the start date of Phase 2 may necessarily cause the start dates of the tasks comprising Phase 2 to be similarly pushed out to a future date. As a result, the tasks scheduled as a part of the sub-project schedule 340 may likewise be pushed out to future dates as a result of the change in the parent/master schedule 310.
Similarly, a change made in the scheduling of a sub-task in the sub-project schedule 340 may cause a disruption in the schedule of a phase or task scheduled in an upstream sub-project schedule or parent/master project schedule.

If such schedule changes are automatically made to each of the associated project schedules without warning to the owners/managers of the associated project schedules, the resulting project schedules become less reliable to their respective owners/managers and, at best, serve as snapshots of the presently amended project and sub-project schedules. According to embodiments of the present invention, the establishment of a parent/child hierarchical relationship between the master project schedule and any associated child sub-project schedules allows for an automated notification and acceptance/rejection/counter change process to occur between owners/managers of various related project schedules so that each of the project schedules may be more informative and manageable by their respective owners/managers.
Having described an exemplary operating environment for embodiments of the present invention with reference to Figs. 1 and 2 and having described hierarchically-related project schedules with reference to Fig. 3, Fig. 4 is a flow diagram showing an illustrative routine for creating and managing a project schedule comprised of a parent (master) project schedule and one or more hierarchically-related sub-project schedules.
The routine 400 begins at start block 405 and proceeds to block 410 where an owner/manager of a master project prepares and publishes a master/parent project schedule such as the parent project schedule 310 illustrated in Fig. 3. As described above with reference to Fig. 2, the owner/manager of the master project may prepare the master project schedule 310 using the computing system 220, and the master project schedule 310 may be published to and stored at the project management server/database 210 via the distributed computing environment 200.
At block 415, target dates for initiation and completion of individual phases or tasks comprising the master project schedule are established and are passed to owners/managers of sub-projects required for completing the one or more phases or tasks comprising the master project. At block 420, the owners/managers of the one or more sub-projects create individual sub-project schedules 320, 340, illustrated in Fig. 3, required for completing phases and tasks required by each sub-project for ultimately completing the master project. Once the individual sub-project schedules are prepared, those project schedules are published to the project management server/database 210, as described above with reference to Fig. 2.
At block 425, a hierarchical relationship is established at the project management server/database 210 between the master project schedule 310 and the S associated sub-project schedules 320, 340. As described above with reference to Fig. 2, the project management server/database 210 includes a relational database that may be utilized in accordance with embodiments of the present invention for relating phases or tasks of one project schedule with associated phases or tasks of a hierarchically-related parent project schedule or sub-project schedule. According to embodiments of the present invention, changes affected to data in a first project schedule that is related to data contained in a second project schedule does not automatically effect changes to the related data contained in the second project schedule.
Instead, according to embodiments of the present invention, changes to data in the first project schedule cause a notification to be sent to the owner/manager of the second project schedule to allow the owner/manager of the second project schedule to accept the change, reject the change, or propose a different change. Thus, changes made to data in the first project schedule do not automatically affect changes to data in the second project schedule without warning to the owner/manager of the second project schedule. For example, consider that a master project schedule includes three phases associated with the construction of a house where Phase 1 includes general framing, Phase 2 includes electrical work, and Phase 3 includes plumbing work.
Consider that a first sub-project schedule 320 includes scheduling data associated with three tasks required for completion of Phase 2 in the master project schedule (electrical work). Consider further that a second sub-project schedule 340 includes three sub-tasks associated with completion of Task 2 of the first sub-project schedule, for example, three sub-tasks associated with completion of a portion of the electrical work.
Establishment of a hierarchical relationship between the three example project schedules includes establishment of the first sub-project schedule 320 as having a child relationship with the parent project schedule 310 and establishment of the second sub project schedule 340 as having a child relationship with the first sub-project schedule 320. According to embodiments of the present invention, if the owner/manager of the parent project schedule 310 increases or decreases the duration of time associated with Phase 2 of the parent project schedule 310, a notification is automatically sent to the owner/manager of the first sub-project schedule 320 because data associated with the first project schedule 320 is related to data representing the amended Phase 2 schedule in the parent project schedule 310. If a change is made to data contained in the first sub-project schedule 320 because of the change submitted from the parent project schedule 310 that affects related data contained in the second sub-project schedule 340, a notification will likewise be sent to the owner/manager of the second sub-project schedule 340.
Scheduling changes submitted from a parent project schedule or sub-project schedule to a sub-project schedule having a child relationship with the submitting project schedule may be accepted by the receiving sub-project owner/manager, or a counterproposal may be submitted back up the hierarchical structure to the submitting parent project or sub-project. If a change received by a sub-project owner/manager is accepted, the change is automatically made to data contained in the receiving and accepting sub-project schedule. If a counter change is submitted by the receiving sub-project schedule owner/manager, the receiving parent project schedule owner/manager may accept the counter change, reject the counter change, or submit yet another counter change back down to the submitting sub-proj ect management owner/manager. Once any change is accepted by a given project schedule owner/manager, as described herein, then a notification is automatically sent to any downstream sub-project schedule whose data is related to data in the changed project schedule and which is affected by the change.
Continuing with the description of the routine 400 illustrated in Fig. 4, at block 430, a change is submitted by the owner/manager of the given sub-project schedule 320 up to the owner/manager of a parent project schedule 310. For example, considering the example described above, the owner/manager of a first sub-project schedule may submit a change requiring that the electrical work for a house construction project is to be extended by one week past the originally established target date. At block 435, because data changed in the first sub-project schedule 320 is related to data contained in the parent project schedule 310 rather than automatically changing related data in the parent project schedule 310, a notification is submitted to the owner/manager of the parent project schedule 310 to alert the owner/manager of the change submitted by the first sub-project schedule 320 owner/manager. As should be understood by those skilled in the art, notification sent to parent project schedule owner/manager may be automatically forwarded via an electronic mail application 130, or the notification may be submitted to the owner/manager of the parent project schedule 310 through any other suitable notification means including instant messaging, telephonic notification, and the like.
At block 440, a determination is made as to whether the owner/manager of the parent project schedule 310 accepts the change made by the owner/manager of the first sub-project schedule 320. According to an embodiment of the present invention, the owner/manager of the master project schedule 310 may be presented with a preview of what the master project schedule 310 and any related sub-project schedules will look like if the proposed change is accepted by the owner/manager of the master project schedule 310. If the owner/manager of the parent project schedule 310 does not accept the change, the routine proceeds to block 445, and the submitting sub-project schedule owner/manager is notified that the parent project schedule owner/manager does not accept the submitted change. As described above, the owner/manager of the parent project schedule 310 may submit a counter change back to the originally submitting sub-project owner/manager, or the parent project schedule owner/manager may simply reject the proposed change. Returning back to block 440, if the owner/manager of the parent project schedule 310 does accept the change from the sub-project schedule owner/manager, the change is persisted in the submitting first sub-project schedule, and the change is automatically made in the accepting parent project schedule 310.
At block 450, a notification is then sent to any additional sub-project schedule owner/managers whose data will be affected by the accepted change. For example, if the change made and accepted to data contained in the first sub-project schedule 320 is related to data contained in a second sub-project schedule 340 having a child relationship to the first sub-project schedule 320, a notification is then sent to the owner/manager of the second sub-project schedule 340 regarding a change in the data.
For example, the accepted and persisted change to the data in the first sub-project schedule 320 may cause the initiation of a sub task contained in the second sub-project schedule 340 to be pushed out by two weeks.
At block 455, a determination is made as to whether the notified sub-project schedule owner/manager accepts the change required by the change in the upstream project schedules, described above. If the first notified sub-project schedule owner/manager accepts the changes caused to his/her schedule, the routine proceeds to block 460, and the sub-project schedule is changed, and required notification to additional downstream sub-project schedule owners/managers is made, as described herein. If the receiving sub-project schedule owner/manager does not accept the change caused by the upstream changes, the routine proceeds to block 465, and a responsive counter change may be submitted back up to upstream project schedule or sub-project schedule owners/managers. For example, if initiation of a particular sub task of the second sub-project schedule 340 must be pushed out two weeks because of a change affected to the first sub-project schedule 320 and accepted by the owner/manager of the parent project schedule 310, the owner/manager of the second sub-project schedule 340 may submit a counter change proposing that the initiation of the affected sub-task be pushed out three weeks instead of two weeks. At block 470, a determination is made as to whether the parent or master project schedule or sub-project schedule owner/manager accepts the proposed counter change by the owner/manager of the second sub-project schedule 340. If the owner/manager of the receiving master/parent project schedule accepts the counter change proposed by the owner/manager of the second sub-project schedule 340, the routine proceeds back to block 450 for notification to other affected sub-project schedule owners/managers.
As described herein, a method and system are provided for establishing a hierarchical relationship and communications between a parent or master project schedule and sub-project schedules including tasks and phases required for completion of the parent or master project. It will be apparent to those skilled in the art that various modifications or variations may be made in the present invention without departing from the scope or spirit of the invention. Other embodiments of the present invention will be apparent to those skilled in the art from consideration of the specification and practice of the invention as disclosed herein.

Claims (20)

CLAIMS:
1. A method for communicating scheduling changes in a project management schedule, comprising:
receiving scheduling data for a project;
generating a project schedule for the project;
generating a project schedule for any sub-projects comprising the project;
establishing a hierarchical relationship between the project and the any sub-projects comprising the project;
submitting a scheduling change from the project schedule to any of the sub-project schedules that are affected by the scheduling change; and automatically sending a notification of the scheduling change to any of the sub-project schedules affected by the scheduling change prior to persisting the scheduling change to any of the affected sub-project schedules.
2. The method of Claim 1, further comprising:
in response to receipt of the notification of the scheduling change, accepting the scheduling change by the sub-projects that are affected by the scheduling change; and persisting the scheduling change to any of the sub-project schedules that are affected by the scheduling change.
3. The method of Claim 1, further comprising:
in response to receipt of the notification of the scheduling change, submitting a counter scheduling change from one of the affected sub-project schedules to the project schedule; and if the project schedule accepts the counter scheduling change, persisting the counter scheduling change to project schedule and to one of the affected sub-project schedules.
4. The method of Claim 3, further comprising, after persisting the counter scheduling change to project schedule and to one of the affected sub-project schedules, submitting the counter scheduling change from the project schedule to any other of the sub-project schedules that are affected by the counter scheduling change.
5. The method of Claim 1, further comprising allowing changes to be made to the project schedule or to any of the sub-project schedules without causing a corresponding change to any other project schedule until a change notification is sent from the changing project schedule or changing sub-project schedule to a project schedule or sub-project schedule that is affected by the changes.
6. A method for independently managing project schedules comprising an overall project management schedule, comprising:
receiving scheduling data for a project;
generating project schedules for the project and for one or more sub-projects comprising the project;
establishing a hierarchical relationship between the generated project schedules for allowing communications between the hierarchically-related project schedules; and allowing changes to be made to a first project schedule without causing a corresponding change to any other hierarchically-related project schedule until a change notification is sent from the first project schedule to a second project schedule that is affected by the changes.
7. The method of Claim 6, further comprising:
submitting a scheduling change from a first project schedule to a second hierarchically-related project schedule; and automatically sending a notification of the scheduling change from the first project schedule to the second hierarchically-related project schedule prior to persisting the scheduling change to the second hierarchically-related project schedule.
8. The method of Claim 7, further comprising:
in response to receipt of the notification of the scheduling change, accepting the scheduling change by the second hierarchically-related project schedule; and persisting the scheduling change to the second hierarchically-related project schedule.
9. The method of Claim 8, further comprising:
in response to receipt of the notification of the scheduling change, submitting a counter scheduling change from the second hierarchically-related project schedule to the first project schedule; and if the first project schedule accepts the counter scheduling change, persisting the counter scheduling change to first project schedule and to the second hierarchically-related project schedule.
10. The method of Claim 9, further comprising, after persisting the counter scheduling change to the first project schedule and to the second hierarchically-related project schedule, submitting the counter scheduling change from the first project schedule to any other hierarchically-related project schedule that is affected by the counter scheduling change.
11. A computer-readable medium containing computer-executable instructions which when executed by a computer perform a method for communicating scheduling changes in a project management schedule, comprising:
receiving scheduling data for a project;
generating a project schedule for the project;
generating a project schedule for any sub-projects comprising the project;
establishing a hierarchical relationship between the project and the any sub-projects comprising the project;
submitting a scheduling change from the project schedule to any of the sub-project schedules that are affected by the scheduling change; and automatically sending a notification of the scheduling change to any of the sub-project schedules affected by the scheduling change prior to persisting the scheduling change to any of the affected sub-project schedules.
12. The computer-readable medium of Claim 11, further comprising:
in response to receipt of the notification of the scheduling change, accepting the scheduling change by the sub-projects that are affected by the scheduling change; and persisting the scheduling change to any of the sub-project schedules that are affected by the scheduling change.
13. The computer-readable medium of Claim 11, further comprising:
in response to receipt of the notification of the scheduling change, submitting a counter scheduling change from one of the affected sub-project schedules to the project schedule; and if the project schedule accepts the counter scheduling change, persisting the counter scheduling change to project schedule and to one of the affected sub-project schedules.
14. The computer-readable medium of Claim 13, further comprising, after persisting the counter scheduling change to project schedule and to one of the affected sub-project schedules, submitting the counter scheduling change from the project schedule to any other of the sub-project schedules that are affected by the counter~
scheduling change.
15. The computer-readable medium of Claim 11, further comprising allowing changes to be made to the project schedule or to any of the sub-project schedules without causing a corresponding change to any other project schedule until a change notification is sent from the changing project schedule or changing sub-project schedule to a project schedule or sub-project schedule that is affected by the changes.
16. ~A computer-readable medium containing computer-executable instructions which when executed by a computer perform a method for independently managing project schedules comprising an overall project management schedule, comprising:
receiving scheduling data for a project;
generating project schedules for the project and for one or more sub-projects comprising the project;
establishing a hierarchical relationship between the generated project schedules for allowing communications between the hierarchically-related project schedules; and allowing changes to be made to a first project schedule without causing a corresponding change to any other hierarchically-related project schedule until a change notification is sent from the first project schedule to a second project schedule that is affected by the changes.
17. ~The computer-readable medium of Claim 16, further comprising:
submitting a scheduling change from a first project schedule to a second hierarchically-related project schedule; and automatically sending a notification of the scheduling change from the first project schedule to the second hierarchically-related project schedule prior to persisting the scheduling change to the second hierarchically-related project schedule.
18. ~The computer-readable medium of Claim 17, further comprising:
in response to receipt of the notification of the scheduling change, accepting the~
scheduling change by the second hierarchically-related project schedule; and persisting the scheduling change to the second hierarchically-related project schedule.
19. ~The computer-readable medium of Claim 18, further comprising:
in response to receipt of the notification of the scheduling change, submitting a counter scheduling change from the second hierarchically-related project schedule to the first project schedule; and if the first project schedule accepts the counter scheduling change, persisting the counter scheduling change to first project schedule and to the second hierarchically-related project schedule.
20. ~The computer-readable medium of Claim 19, further comprising, after persisting the counter scheduling change to the first project schedule and to the second hierarchically-related project schedule, submitting the counter scheduling change from the first project schedule to any other hierarchically-related project schedule that is affected by the counter scheduling change.
CA002509867A 2004-06-15 2005-06-14 Hierarchical projects in a computer-enabled project management method and system Abandoned CA2509867A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US10/868,661 2004-06-15
US10/868,661 US7734491B2 (en) 2004-06-15 2004-06-15 Hierarchical projects in a computer-enabled project management method and system

Publications (1)

Publication Number Publication Date
CA2509867A1 true CA2509867A1 (en) 2005-12-15

Family

ID=34940174

Family Applications (1)

Application Number Title Priority Date Filing Date
CA002509867A Abandoned CA2509867A1 (en) 2004-06-15 2005-06-14 Hierarchical projects in a computer-enabled project management method and system

Country Status (13)

Country Link
US (1) US7734491B2 (en)
EP (1) EP1607896A1 (en)
JP (1) JP4851123B2 (en)
KR (1) KR101176647B1 (en)
CN (1) CN1734483A (en)
AU (1) AU2005202447B2 (en)
BR (1) BRPI0502335A (en)
CA (1) CA2509867A1 (en)
MX (1) MXPA05006431A (en)
MY (1) MY143438A (en)
RU (1) RU2400814C2 (en)
TW (1) TW200620036A (en)
ZA (1) ZA200504810B (en)

Families Citing this family (45)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050278208A1 (en) * 2004-06-15 2005-12-15 Microsoft Corporation Method and system for restarting a project management system scheduling engine based on user input of contractual start/finish data
EA201400189A1 (en) * 2004-06-29 2014-09-30 Текстура Корпорейшн SYSTEM AND METHOD OF PAYMENT MANAGEMENT IN CONSTRUCTION
TW200634590A (en) * 2005-03-30 2006-10-01 wen-xian Chen Project-planning method and system
US20070156484A1 (en) * 2005-12-29 2007-07-05 Sandra Fischbach Cross company project management
US20070260502A1 (en) * 2006-05-04 2007-11-08 Microsoft Corporation Project resource plans
US20070266327A1 (en) * 2006-05-10 2007-11-15 Josh Ritcher Entertainment project management system
US20080004925A1 (en) * 2006-06-29 2008-01-03 Bangel Matthew J Multi-site project management
US20080086353A1 (en) * 2006-10-04 2008-04-10 Microsoft Corporation Server level summary information of resource utilization
US8880615B2 (en) * 2006-12-15 2014-11-04 International Business Machines Corporation Managing a workflow using an instant messaging system to gather task status information
US8249906B2 (en) * 2007-02-12 2012-08-21 Pma Technologies, Llc Interactive graphics-based planning systems
JP5440780B2 (en) * 2007-02-26 2014-03-12 日本電気株式会社 Message notification method, business management apparatus, and computer program
US7996774B1 (en) * 2007-02-28 2011-08-09 Emc Corporation Hierarchical display of project information in a collaboration environment
US8666794B1 (en) * 2007-03-26 2014-03-04 Sprint Communications Company L.P. Project management tool
US10255583B2 (en) * 2007-05-01 2019-04-09 Oracle International Corporation Nested hierarchical rollups by level using a normalized table
US20080300945A1 (en) * 2007-05-31 2008-12-04 Michel Shane Simpson Techniques for sharing resources across multiple independent project lifecycles
US20090006147A1 (en) * 2007-06-27 2009-01-01 Harirajan Padmanabhan Method and system for defining and managing information technology projects based on conceptual models
US7962889B2 (en) 2007-07-31 2011-06-14 Novell, Inc. Techniques for instantiating and configuring projects
US20090043621A1 (en) * 2007-08-09 2009-02-12 David Kershaw System and Method of Team Performance Management Software
US20090048894A1 (en) * 2007-08-14 2009-02-19 Michel Shane Simpson Techniques for propagating changes in projects
US10395187B2 (en) * 2008-02-11 2019-08-27 Clearshift Corporation Multilevel assignment of jobs and tasks in online work management system
JP5164068B2 (en) * 2008-04-15 2013-03-13 インターナショナル・ビジネス・マシーンズ・コーポレーション Production schedule editing system, method and program
US20090313058A1 (en) * 2008-06-12 2009-12-17 Dunin Technologie Inc. Tool, method and system for project management
US20100031262A1 (en) * 2008-07-31 2010-02-04 Baird-Gent Jill M Program Schedule Sub-Project Network and Calendar Merge
US9009725B2 (en) * 2008-09-02 2015-04-14 At&T Mobility Ii Llc System of growth and automated migration
US9129256B2 (en) * 2009-07-24 2015-09-08 Oracle International Corporation Enabling collaboration on a project plan
US20110099549A1 (en) * 2009-10-27 2011-04-28 Verizon Patent And Licensing Inc. Methods, systems and computer program products for a reminder manager for project development
US20110131139A1 (en) * 2009-12-01 2011-06-02 International Business Machines Corporation Integrated earned value management workflow
JP2011192078A (en) * 2010-03-15 2011-09-29 Ricoh Co Ltd Task managing device and task management program
FR2963837B1 (en) * 2010-08-10 2012-08-31 Air Liquide MULTI-LEVEL PROCESSING FOR OPTIMIZING ONE OR MORE FLUID SEPARATION UNITS
US20120290347A1 (en) * 2010-08-10 2012-11-15 King Fahd University Of Petroleum And Minerals Progress monitoring method
US8683473B2 (en) * 2011-05-27 2014-03-25 International Business Machines Corporation Dynamic task association between independent, unrelated projects
US9946988B2 (en) * 2011-09-28 2018-04-17 International Business Machines Corporation Management and notification of object model changes
US20130218625A1 (en) * 2012-02-22 2013-08-22 International Business Machines Corporation Utilizing historic projects to estimate a new project schedule based on user provided high level parameters
FI20125700A (en) * 2012-06-21 2013-12-22 Tekla Corp Shared data with relationship information
US9530112B2 (en) * 2013-04-17 2016-12-27 Globalfoundries Inc. Common conditions for past projects as evidence for success causes
CN103226758A (en) * 2013-05-08 2013-07-31 灏域联华科技(北京)有限公司 Project development management method
US9202188B2 (en) 2013-08-30 2015-12-01 International Business Machines Corporation Impact analysis of change requests of information technology systems
US20150371168A1 (en) * 2014-06-22 2015-12-24 Wamoozle Inc. Collaborative project management platform using a place-centric method and system for capturing and organizing project information
US20160026952A1 (en) * 2014-07-28 2016-01-28 Robin Systems, Inc. System and method performing job management
US11540556B2 (en) 2015-11-05 2023-01-03 Philip Morris Products S.A. Homogenized tobacco material with improved volatile transfer
CN107231367B (en) * 2017-06-21 2021-03-19 北京奇虎科技有限公司 Automatic notification method and device for signature message and server
RU2686031C1 (en) * 2018-02-22 2019-04-23 Общество с ограниченной ответственностью "ВИЗЕКС ИНФО" Method and device for processing and analyzing large data characterizing various processes
US11257035B2 (en) * 2018-09-10 2022-02-22 Sap Se Splitting a task hierarchy
WO2020118638A1 (en) 2018-12-13 2020-06-18 Entit Software Llc Project management visualization interface
US11402820B2 (en) * 2020-03-17 2022-08-02 Consulting Engineers, Corp. Method and system for building framing and manufacturing system

Family Cites Families (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5381332A (en) * 1991-12-09 1995-01-10 Motorola, Inc. Project management system with automated schedule and cost integration
US5548506A (en) * 1994-03-17 1996-08-20 Srinivasan; Seshan R. Automated, electronic network based, project management server system, for managing multiple work-groups
US5765140A (en) * 1995-11-17 1998-06-09 Mci Corporation Dynamic project management system
JP3708199B2 (en) * 1996-01-17 2005-10-19 株式会社東芝 Concurrent engineering support system and concurrent engineering support method
AUPN773496A0 (en) * 1996-01-25 1996-02-15 Task Solutions Pty Ltd Task management system
JPH10240804A (en) 1997-02-21 1998-09-11 Nec Corp Project management system
US6609100B2 (en) * 1997-03-07 2003-08-19 Lockhead Martin Corporation Program planning management system
US6351734B1 (en) * 1998-09-09 2002-02-26 Unisys Corporation System and method for resource allocation and planning
JP4057171B2 (en) * 1998-11-17 2008-03-05 富士通株式会社 Information synchronization system and recording medium
US7139719B1 (en) * 1999-10-08 2006-11-21 I2 Technologies Us, Inc. System for scheduling product planning
US6581040B1 (en) * 2000-02-18 2003-06-17 Daniel B. Wright Project specific communications system and method
US6714829B1 (en) * 2000-06-22 2004-03-30 Thomas K F Wong Dual path scheduling method
US7096222B2 (en) * 2000-09-01 2006-08-22 Borland Software Corporation Methods and systems for auto-instantiation of storage hierarchy for project plan
JP2002149747A (en) * 2000-11-10 2002-05-24 Aqura Home Co Ltd Process control method using electronic process table
WO2002103602A1 (en) * 2001-06-07 2002-12-27 Togethersoft Corporation Methods and systems for linking tasks to workflow
US7406432B1 (en) * 2001-06-13 2008-07-29 Ricoh Company, Ltd. Project management over a network with automated task schedule update
US7349863B1 (en) * 2001-06-14 2008-03-25 Massachusetts Institute Of Technology Dynamic planning method and system
US7644007B2 (en) * 2002-06-17 2010-01-05 King Fahd University Of Petroleum & Minerals Method and apparatus for finance-based scheduling of construction projects
JP2004139588A (en) 2002-09-25 2004-05-13 Smg Kk Device, system and program for managing project
JP2004240486A (en) * 2003-02-03 2004-08-26 Hitachi Ltd Change management method and apparatus for project

Also Published As

Publication number Publication date
MY143438A (en) 2011-05-13
KR101176647B1 (en) 2012-08-23
MXPA05006431A (en) 2005-12-19
JP2006004431A (en) 2006-01-05
ZA200504810B (en) 2007-03-28
AU2005202447A1 (en) 2006-01-05
CN1734483A (en) 2006-02-15
BRPI0502335A (en) 2006-02-07
TW200620036A (en) 2006-06-16
RU2400814C2 (en) 2010-09-27
US20050278209A1 (en) 2005-12-15
AU2005202447B2 (en) 2010-03-18
EP1607896A1 (en) 2005-12-21
JP4851123B2 (en) 2012-01-11
RU2005118392A (en) 2006-12-20
KR20060048381A (en) 2006-05-18
US7734491B2 (en) 2010-06-08

Similar Documents

Publication Publication Date Title
US7734491B2 (en) Hierarchical projects in a computer-enabled project management method and system
US11087281B2 (en) System and method of commitment management
US7496886B2 (en) Method and system for providing cross project commitments
JP4986418B2 (en) Method and system for caching and synchronizing project data
US7360164B2 (en) Collaboration launchpad
US7930268B2 (en) Workflow method, system, and data structure
US8032635B2 (en) Grid processing in a trading network
US7640506B2 (en) Method and apparatus for viewing and managing collaboration data from within the context of a shared document
US20160112476A1 (en) Integrated real time collaboration experiences with online workspace
JP2020500354A (en) Improve efficiency in task management applications
JP6144730B2 (en) A method adapted to be used for commercial transactions
US20140310045A1 (en) Generating and Displaying a Calendar Event Recurrence Preview
US20140310044A1 (en) Transmitting an Electronic Message to Calendar Event Invitees
US20050120108A1 (en) Communication tagging
JP2009507313A (en) Free information data service
CN111507689A (en) Service processing method, device, equipment and computer readable storage medium
KR101109292B1 (en) Active agenda
AU2002258345B2 (en) An enterprise knowledge and information acquisition, management and communications system with intelligent user interfaces
CN112749948A (en) Information processing method and device for project management
JP2002073921A (en) Schedule management system and method and storage medium storing schedule management program

Legal Events

Date Code Title Description
EEER Examination request
FZDE Discontinued

Effective date: 20150616